Skip to content
Residential / Group Housing · 6 buildings · 21 unitsRERA P99000078084

Prime One

Deedo IDDP-PAL-G4D1

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 0% of its units are booked.

Vangaon, Palghar 401103 · by Primeville Developers Llp

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 21 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 25 Nov 2024, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000078084
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900007808425 Nov 202431 Dec 202730 Apr 2028Primeville Developers LLPProject page
Documents66

1 document held by Deedo, 65 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan primeville.pdf · uploaded 29 May 2024Source

Legal

  • Other – LegalPrimeville LLP Agreement_compressed.pdf · uploaded 29 May 2024Source
  • Legal Title reporttitle primeville 44-24.pdf · uploaded 13 Jun 2024Source
  • Legal Title reporttitle primeville 44-18.pdf · uploaded 13 Jun 2024Source
  • Declaration Form BForm-B (2).pdf · uploaded 21 Nov 2024Source

Migrated

  • 1 PAN Cardpan primeville.pdf · uploaded 29 May 2024Source
  • 1 Copy of Layout Approval (in case of layout)layout (3).pdf · uploaded 29 May 2024Source
Show all 66 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentbandhkam paravangi_compressed.pdf · uploaded 29 May 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentrow house no 6.pdf · uploaded 29 May 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding no1_compressed.pdf · uploaded 29 May 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentrou house 2 to 5.pdf · uploaded 29 May 2024Source
  • 1 Other – LegalPrimeville LLP Agreement_compressed.pdf · uploaded 29 May 2024Source
  • 1 Copy of the legal title reporttitle primeville 44-18.pdf · uploaded 13 Jun 2024Source
  • 2 Copy of the legal title reporttitle primeville 44-24.pdf · uploaded 13 Jun 2024Source
  • 1 CERSAI detailsDeclaration Cersai.pdf · uploaded 22 Jun 2024Source
  • 1 a Details of encumbrances concerned to FinanceDeclaration Finance encumbrances (3).pdf · uploaded 19 Oct 2024Source
  • 2 a Details of encumbrances concerned to Financelegal encumbrance declaration.pdf · uploaded 19 Oct 2024Source
  • 1 Proforma of Allotment letterDraft Allotment Letter.pdf · uploaded 19 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Final Form-1 Prime.pdf · uploaded 19 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Final revised.pdf · uploaded 19 Oct 2024Source
  • 1 Declaration about Commencement Certificatecc declaration.pdf · uploaded 19 Oct 2024Source
  • 1 Deviation Report with respect to Allotment letterallotment deviation report.pdf · uploaded 19 Oct 2024Source
  • 1 b Details of encumbrances concerned to LegalDeclaration Finance encumbrances (3).pdf · uploaded 19 Oct 2024Source
  • 2 b Details of encumbrances concerned to Legallegal encumbrance declaration.pdf · uploaded 19 Oct 2024Source
  • 1 Deviation Report with respect to model copy of Agreementagreement deviation report.pdf · uploaded 19 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest Navin Parekh.pdf · uploaded 19 Oct 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest puneet mehra.pdf · uploaded 19 Oct 2024Source
  • 3 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest vishal parekh.pdf · uploaded 19 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectSecured unsecured funds declaration.pdf · uploaded 19 Oct 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentGmail - CC Issued by Collector Palghar at village Vangaon Taluka Dhanu Dist Palghar Ser No 44 plot no 18 and 24 Order date 14 May 2024.pdf · uploaded 11 Nov 2024Source
  • 1 Other – TechnicalGmail - CC Issued by Collector Palghar at village Vangaon Taluka Dhanu Dist Palghar Ser No 44 plot no 18 and 24 Order date 14 May 2024.pdf · uploaded 11 Nov 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)BOB Letter For Rera Prime oneCORRECTED.pdf · uploaded 12 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Primeville LLP Prime One - Form 3 RERA Cert 1 Form 12 Nov 2024 signed.pdf · uploaded 16 Nov 2024Source
  • 2 Other – TechnicalAnnexure-A(Declaration cum undertaking for no duplicate registration).pdf · uploaded 18 Nov 2024Source
  • 1 Declaration in FORM BForm-B (2).pdf · uploaded 21 Nov 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format-A cORRECTED.pdf · uploaded 22 Nov 2024Source
  • 1 Proforma of Agreement for sale1 Proforma of Agreement for sale (1).pdf · uploaded 22 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 Prime one_compressed.pdf · uploaded 22 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Primeville LLP Prime One - Form 3 RERA Cert 2 Form 29 Jan 2025 1.pdf · uploaded 22 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 Prime One.pdf · uploaded 22 Mar 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)formate A (about separate bank acc).pdf · uploaded 22 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)formate B ( bank Letter ).pdf · uploaded 22 Mar 2025Source
  • Form 5 (FY 2024-2025)PrimeVille_Form 5 2025 signed.pdf · uploaded 3 Oct 2025Source
  • Withdrawal Update Form 1Form 1 Sep 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 1FORM 1 DEC 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 2Form-2 Sep 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 2FORM-2 DEC 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 1FORM 1 UPTO 31ST MAR 2026 PRIME ONE.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 2FORM 2 PRIME ONE AS ON 31ST MAR 2026.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 3Prime One - Form 3 RERA.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 1form 1 prime one (30-6-2026).pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 2form 2 JUNE 2026.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 3Form-3 June 2026.pdf · uploaded 18 Jul 2026Source

Technical

  • Documentrow house no 6.pdf · uploaded 29 May 2024Source
  • Documentrou house 2 to 5.pdf · uploaded 29 May 2024Source
  • DocumentBuilding no1_compressed.pdf · uploaded 29 May 2024Source
  • Documentlayout (3).pdf · uploaded 29 May 2024Source
  • Other – TechnicalGmail - CC Issued by Collector Palghar at village Vangaon Taluka Dhanu Dist Palghar Ser No 44 plot no 18 and 24 Order date 14 May 2024.pdf · uploaded 11 Nov 2024Source
  • Other – TechnicalAnnexure-A(Declaration cum undertaking for no duplicate registration).pdf · uploaded 18 Nov 2024Source

Technical (Architect)

  • Documentform 1 Prime one_compressed.pdf · uploaded 22 Mar 2025Source
  • Documentform 1 prime one (30-6-2026).pdf · uploaded 18 Jul 2026Source

Technical (Engineer)

  • Documentform 2 Prime One.pdf · uploaded 22 Mar 2025Source
  • Documentform 2 JUNE 2026.pdf · uploaded 18 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—21 units in all
Address
Survey No. 44/18 And 44/24, Vangaon-Chinchani Road, Vangaon WestPIN 401103
Village
Vangaon, Dahanu taluka
Land area for this project
1,227 sq m (13,207 sq ft)
Permissible built-up area
3,225 sq m (34,709 sq ft)
Sanctioned built-up area
1,225 sq m (13,181 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
21
Developed in phases
Yes

Land as published on MahaRERA's project page

SURVEY NO. 44/18 AND 44/24

Boundaries

North
9 Mtr Road
South
Adj S No 43
East
Adj Plot No 17 And 25
West
Adj Plot No 19 And 23

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking21 units

21 units registered

— · 21 units
BuildingTypeCarpet areaUnits
Rh-01——1
Rh-02——1
Rh-03——1
Rh-04——1
Rh-05——1
Yash——16

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectCreative Associates—
Chartered accountantSujoy P Mehta And Associates—
EngineerCentreline Consultants & Engineers—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology