RERA projects in Vangaon
8 projects under 9 MahaRERA registrations, registered 2018–2025. 56% have a completion date extended beyond the one promised.
Locality
8RERA projects
9Registrationssome projects hold several
5Completion still due4 past their completion date
4 monthsMedian extension beyond promised date56% of registrations extended
0Regulatory casesnone on MahaRERA's lists
18Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 2 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 3 |
| 2022 | 1 |
| 2023 | 0 |
| 2024 | 2 |
| 2025 | 1 |
Projects in Vangaon
8 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Samya OnePrimeville Developers LLP | P99000080898 | 1 Aug 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| TanishqRajvan Lifespaces LLP | P99000055111, P99000078341 | 4 Mar 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Tanishq H And I WingPuneet Developers | P99000047114 | 10 Oct 2022 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Puneet Developers - Tanishq F And G WingPuneet Developers | P99000032306 | 29 Dec 2021 | 31 Jul 2025 | 31 Jul 2025 | Promised date passed | 0 |
| Rajvan Lifespaces LLP -Tanishq Gold C WingRajvan Lifespaces LLP | P99000031616 | 3 Nov 2021 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Galaxy ResidencyMahashakti Enterprises | P99000029336 | 18 May 2021 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Parks Developers LLP - Tanishq Gold - Phase 1Parks Developers LLP | P99000015423 | 23 Feb 2018 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| Prutha ResidencyM/s Aum Jivdani Associates | P99000014796 | 2 Jan 2018 | 16 Dec 2021 | 15 Dec 2024 | Extended 36 mo | 0 |
Other localities in Dahanu
Most active promoters
By projects registered here, as named on MahaRERA.
- Puneet Developers2 projects
- Rajvan Lifespaces LLP2 projects
- Mahashakti Enterprises1 project
- M/s Aum Jivdani Associates1 project
- Parks Developers LLP1 project
- Primeville Developers LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology