Ashagad, Palghar

5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects4
Registrations4
Completion still due31 past their date
Median extension4 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists
Ashagad market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Projects in Ashagad

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Samruddhi ApartmentVishesh Bharat PandyaPM124000260098330 Jun 202631 Dec 202731 Dec 2027Not yet due0
Shambhavi Row Houses Phase 2Jayesh Balvant JaniP9900005194513 Jul 202330 Dec 202830 Apr 2029Extended 4 mo0
Shambhavi ApartmentsJayesh Balvant JaniP990000513998 Jun 202330 Dec 202830 Apr 2029Extended 4 mo0
Shambhavi Row HousesJayesh Balvant JaniP9900002517120 Mar 202030 Dec 202530 Dec 2025Promised date passed0

Most active promoters

  1. Jayesh Balvant Jani3 projects
  2. Vishesh Bharat Pandya1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology