RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P99000078084
Prime One · Vangaon, Palghar · Primeville Developers Llp
Promised for 31 Dec 2027, extended to 30 Apr 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P99000078084
Is Prime One delayed?
Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P99000078084. The completion date moved from 31 Dec 2027 to 30 Apr 2028.
Who is the promoter?
MahaRERA records Primeville Developers Llp as the promoter of P99000078084.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P99000078084.
Answers are generated from the record.