Vikas Nagar Phase I
Deedo IDDP-NSK-J4AMIts promised completion date, Jun 2024, has passed and MahaRERA does not show it completed; 1 listing or order with MahaRERA on record; 23% of its units are booked.
Soyagaon (Ct), Nashik 423203 · by Shree Sanket Developers · 0% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jun 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 5 Aug 2019, completion promised 21 Jun 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
11 buildings
Open a building to see every flat, floor by floor.
- Block A2 floors · 30 units0% booked
- Block B2 floors · 20 units0% booked
- Block B12 floors · 7 units43% booked
- Block C2 floors · 24 units67% booked
- Block D2 floors · 33 units39% booked
- Block E2 floors · 33 units6% booked
- Block F2 floors · 24 units46% booked
- Block G2 floors · 20 units40% booked
- Block H2 floors · 29 units0% booked
- Block I2 floors · 10 units0% booked
- Block J2 floors · 4 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory record1
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Regulatory order7 Nov 2023Matched by RERA number
Regulatory order: PROJECT NAME: Vikas Nagar Phase-I (Regulatory Case No. 73 of 2023) dated 7 November 2023.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51600021855
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600021855 | 5 Aug 2019 | 21 Jun 2024 | 21 Jun 2024 | Shree Sanket Developers | Project page |
Documents84
1 document held by Deedo, 83 filings listed on MahaRERA's project page
Finance
- PAN CardPan card.pdf · uploaded 18 Jul 2019Source
Legal
- OtherPARTNERSHIP DEED.pdf · uploaded 18 Jul 2019Source
- OtherPOWER OF ATTORNY-1-15.pdf · uploaded 18 Jul 2019Source
- OtherMEMORANDUM OF UNDERSTANDING.pdf · uploaded 18 Jul 2019Source
- Legal Title reportTitle 1.pdf · uploaded 18 Jul 2019Source
- Legal Title reportTitle 2.pdf · uploaded 18 Jul 2019Source
- Legal Title reportTitle 3.pdf · uploaded 18 Jul 2019Source
Show all 84 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardPan card.pdf · uploaded 18 Jul 2019Source
- 1 Copy of the legal title reportTitle 1.pdf · uploaded 18 Jul 2019Source
- 2 Copy of the legal title reportTitle 2.pdf · uploaded 18 Jul 2019Source
- 3 Copy of the legal title reportTitle 3.pdf · uploaded 18 Jul 2019Source
- 1 Details of encumbrancesNo Encumbrance Phase I.pdf · uploaded 18 Jul 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentBuilding Permission.pdf · uploaded 18 Jul 2019Source
- 1 Declaration in FORM BAffidavit Phase I.pdf · uploaded 18 Jul 2019Source
- 1 Proforma of Allotment letterAgreement for Sale.pdf · uploaded 18 Jul 2019Source
- 1 OtherPARTNERSHIP DEED.pdf · uploaded 18 Jul 2019Source
- 2 OtherPOWER OF ATTORNY-1-15.pdf · uploaded 18 Jul 2019Source
- 3 OtherMEMORANDUM OF UNDERSTANDING.pdf · uploaded 18 Jul 2019Source
- 1 Copy of Layout Approval (in case of layout)Site Plan.pdf · uploaded 23 Jul 2019Source
- 1 Building Plan Approval (IOD)Building Plan.pdf · uploaded 23 Jul 2019Source
- 1 Certificates of CA (Form 3)CA Certificate Phase I.pdf · uploaded 23 Jul 2019Source
- 1 Declaration about Commencement CertificateVikas Nagar Phase I_Form D.pdf · uploaded 25 Aug 2021Source
- 1 Disclosure of sold/ booked inventoryDisclosure Of Sold- Booked Inventory(VN Phase-1)_compressed (1).pdf · uploaded 20 Sep 2021Source
- 1 CERSAI detailsVN Ph 1.pdf · uploaded 12 Apr 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)From 2A_VN Ph1_31032020.pdf · uploaded 1 Aug 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)From 2A_VN Ph1_31032021.pdf · uploaded 1 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Vikas Nagar P1_Form 5.pdf · uploaded 16 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5_VN Phase 1.PDF · uploaded 9 Dec 2022Source
- 2 a Details of encumbrances concerned to FinanceVN P1_Non Enc Legal.PDF · uploaded 21 Dec 2022Source
- 1 b Details of encumbrances concerned to LegalVN P1_Non Enc Legal.PDF · uploaded 21 Dec 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameVN P1_Sep Ac.PDF · uploaded 21 Dec 2022Source
- 1 Deviation Report with respect to Allotment letterVN P1_Deviation AL.PDF · uploaded 21 Dec 2022Source
- 1 Deviation Report with respect to model copy of AgreementVN P1_Deviation AFS.PDF · uploaded 21 Dec 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A VN Phase 1_2022.pdf · uploaded 19 Jan 2023Source
- 4 OtherReply Non Submission_VN Phase 1.PDF · uploaded 8 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5_VN Phase 1_31032020.pdf · uploaded 14 Feb 2023Source
- 2 Certificates of CA (Form 3)Form 3 - VN Phase 1_31032020.pdf · uploaded 21 Feb 2023Source
- 3 Certificates of CA (Form 3)Form 3 - VN Phase 1_31032021.pdf · uploaded 21 Feb 2023Source
- 4 Certificates of CA (Form 3)Form 3_New Format - VN Phase 1_31032022.pdf · uploaded 21 Feb 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31-03-2020 Vikas Nagar Phase 1_Compressed.pdf · uploaded 22 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31-03-2021 Vikas Nagar Phase 1_Compressed.pdf · uploaded 22 Feb 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31-03-2022 Vikas Nagar Phase 1_Compressed.pdf · uploaded 22 Feb 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM - 2 Phase I Vikas Nagar 2019-20.pdf · uploaded 22 Feb 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM - 2 Phase I Vikas Nagar 2020-21.pdf · uploaded 22 Feb 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Phase I Vikas Nagar 2021-22.pdf · uploaded 22 Feb 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Int_VN_P_1.PDF · uploaded 1 Mar 2023Source
- 1 Other – TechnicalVN Phase 1_Annexure A.PDF · uploaded 23 May 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A VN Phase1_310323.pdf · uploaded 16 Jun 2023Source
- 2 Disclosure of sold/ booked inventoryVN Phase 1_30092023_11zon.pdf · uploaded 25 Nov 2023Source
- 5 Certificates of CA (Form 3)Form 3_ VN Phase 1_300923.pdf · uploaded 28 Nov 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Phase I 2023-24.pdf · uploaded 1 Dec 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Phase I Vikas Nagar 2023-24.pdf · uploaded 1 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Vikas Nagar Phase-1 Rera Certificate.PDF · uploaded 1 Dec 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)VN Form 1_Phase 1_300622.pdf · uploaded 4 Apr 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)VN Form 1_Phase 1 300922.pdf · uploaded 4 Apr 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)VN Form 1_Phase 1 311222.pdf · uploaded 4 Apr 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)VN Form 1_Phase 1 310323.pdf · uploaded 4 Apr 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)VN Form 1 - Phase 1 300623.pdf · uploaded 4 Apr 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)VN Form 1 - Phase 1 311223.pdf · uploaded 4 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)300622 Form 2 - Phase I Vikas Nagar.pdf · uploaded 4 Apr 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)300922 Form 2 - Phase I Vikas Nagar.pdf · uploaded 4 Apr 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)311222 Form 2 - Phase I Vikas Nagar.pdf · uploaded 4 Apr 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)310323 Form 2 - Phase I Vikas Nagar.pdf · uploaded 4 Apr 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)300623 Form 2 - Phase I Vikas Nagar.pdf · uploaded 4 Apr 2024Source
- 6 Certificates of CA (Form 3)Form 3_ VN Phase 1_30062022.pdf · uploaded 4 Apr 2024Source
- 7 Certificates of CA (Form 3)Form 3_ VN Phase 1_30092022.pdf · uploaded 4 Apr 2024Source
- 8 Certificates of CA (Form 3)Form 3_ VN Phase 1_31122022.pdf · uploaded 4 Apr 2024Source
- 9 Certificates of CA (Form 3)Form 3_ VN Phase 1_31032023.pdf · uploaded 4 Apr 2024Source
- 10 Certificates of CA (Form 3)Form 3_ VN Phase 1_30062023.pdf · uploaded 4 Apr 2024Source
- 11 Certificates of CA (Form 3)Form 3_ VN Phase 1_31122023.pdf · uploaded 4 Apr 2024Source
- 3 Disclosure of sold/ booked inventoryVikas Nagar Inventory Sheet Phase I_310324_compressed.pdf · uploaded 25 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5_23-24_VN P 1.PDF · uploaded 20 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)From 2A_VN Ph1_31032024.pdf · uploaded 12 Dec 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentSr No 58 Sanction Cancelletion.pdf · uploaded 5 Feb 2025Source
- 1 Other – TechnicalSr No 58 Sanction Cancelletion.pdf · uploaded 5 Feb 2025Source
Technical
Technical (Architect)
- DocumentVN Form 1 - Phase 1 311223.pdf · uploaded 4 Apr 2024Source
Technical (Engineer)
- Document300623 Form 2 - Phase I Vikas Nagar.pdf · uploaded 4 Apr 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 1 TO 87 EXCEPT PLOT NO 3 4 86 87, 72 S.NO.58/1/4/1/A/B/D
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- Row house234 units in all
- Address
- 1 To 87 Except Plot No 3 4 86 87 And 72 S.no.58/1/4/1/A/B/D, Soyagaon, MalegaonPIN 423203
- Village
- Soyagaon (CT), Malegaon taluka
- Location
- 20.54126, 74.50782
- Land area for this project
- 14,704 sq m (1,58,269 sq ft)
- Permissible built-up area
- 11,766 sq m (1,26,649 sq ft)
- Sanctioned built-up area
- 11,766 sq m (1,26,649 sq ft)
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
1 TO 87 EXCEPT PLOT NO 3 4 86 87 AND 72 S.NO.58/1/4/1/A/B/D
Boundaries
- North
- S No 67 3b
- South
- 9 Meter Road Open Space
- East
- S No 58 Part
- West
- S No 59 60 6 2 60
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking234 units
53 of 234 units booked (23%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Block A | Row house | 52.32 sq m · 563 sq ft | 6 | 0 |
| Block A | Row house | 53.14 sq m · 572 sq ft | 24 | 0 |
| Block B | Row house | 52.96 sq m · 570 sq ft | 2 | 0 |
| Block B | Row house | 52.98 sq m · 570 sq ft | 2 | 0 |
| Block B | Row house | 53.76 sq m · 579 sq ft | 8 | 0 |
| Block B | Row house | 53.8 sq m · 579 sq ft | 8 | 0 |
| Block B1 | Row house | 55.16 sq m · 594 sq ft | 2 | 1 |
| Block B1 | Row house | 56.16 sq m · 605 sq ft | 5 | 2 |
Show all 28 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Block C | Row house | 55.38 sq m · 596 sq ft | 6 | 6 |
| Block C | Row house | 56.2 sq m · 605 sq ft | 18 | 10 |
| Block D | Row house | 52.98 sq m · 570 sq ft | 6 | 6 |
| Block D | Row house | 53.8 sq m · 579 sq ft | 27 | 7 |
| Block E | Row house | 48.94 sq m · 527 sq ft | 6 | 1 |
| Block E | Row house | 49.68 sq m · 535 sq ft | 27 | 1 |
| Block F | Row house | 55.38 sq m · 596 sq ft | 6 | 5 |
| Block F | Row house | 56.2 sq m · 605 sq ft | 18 | 6 |
| Block G | Row house | 48.94 sq m · 527 sq ft | 4 | 4 |
| Block G | Row house | 49.68 sq m · 535 sq ft | 16 | 4 |
| Block H | Row house | 52.32 sq m · 563 sq ft | 5 | 0 |
| Block H | Row house | 53.14 sq m · 572 sq ft | 23 | 0 |
| Block H | Row house | 71.64 sq m · 771 sq ft | 1 | 0 |
| Block I | Row house | 43.88 sq m · 472 sq ft | 1 | 0 |
| Block I | Row house | 44.86 sq m · 483 sq ft | 2 | 0 |
| Block I | Row house | 49.68 sq m · 535 sq ft | 3 | 0 |
| Block I | Row house | 50.42 sq m · 543 sq ft | 4 | 0 |
| Block J | Row house | 48.56 sq m · 523 sq ft | 1 | 0 |
| Block J | Row house | 49.5 sq m · 533 sq ft | 2 | 0 |
| Block J | Row house | 51.58 sq m · 555 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Madhusudan B Kabra | — |
| Chartered accountant | Pranesh Lodha | — |
| Engineer | Santosh Y Kokane | — |
| Other | Hitesh Rajendra Jain | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Soyagaon (Ct)
- Bachhav EmpireRERA P51600080605
All 2 projects in Soyagaon (Ct) · Compare Vikas Nagar Phase I with another project