Shree Sanket Developers

Company or firm · 6 projects · 7 MahaRERA registrations

Projects67 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date60%3 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases1MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Sanket GardenP51600003519Nilgavhan2017Not reported30 Jan 202215 Aug 2023+19 months
Shree Sanket EmpireP51600007618Sangameshwar (Ct)2017Not reported31 Dec 201731 Mar 2024+75 months
Shree Sanket GardenP51600015055Nilgavhan2018Not reported30 Jan 2024—On date
Vikas Nagar Phase IP51600021855Soyagaon (Ct)2019Not reported21 Jun 2024—On date
Vikas Nagar Phase IIP51600021872Malegaon (M Corp.)2019Not reported21 Jun 2024—On date
Sanket HeightsP51600022617Sangameshwar (Ct)2019Not reported31 Dec 2026—On date
Sanket LuxuriaP51600048264Malegaon (M Corp.)2022Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Sanket Garden+19 mo
  • Shree Sanket Empire+75 mo
  • Shree Sanket GardenOn date
  • Vikas Nagar Phase IOn date
  • Vikas Nagar Phase IIOn date
  • Sanket HeightsOn date
  • Sanket LuxuriaOn date

Track record notes

  • 3 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 75 months, for Shree Sanket Empire (P51600007618).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology