Skip to content
Others · 1 building · 16 unitsRERA P51600022757

Gokul 3

Deedo IDDP-NSK-RVHF

MahaRERA shows it completed; no MahaRERA orders on record.

Satpur, Nashik 422012 · by Gokul Infrastructure · 100% of its projects kept the RERA date

DeliveryCompletedAs MahaRERA showsRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 16 Oct 2019, completion promised 30 Dec 2022.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600022757
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160002275716 Oct 201930 Dec 2022—Gokul InfrastructureProject page
Documents27

12 documents held by Deedo, 15 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Form 2

Form 1

Registration certificate

Occupancy / completion certificate

  • Occupancy / completion certificate24 Jan 2023ViewSource
Show all 27 documentsShow fewer documents

Other

Layout plan

Building plan

Allotment letter

Document library

  • Copy of the legal title reportTitle Report - Gokul 3.pdf · uploaded 8 Oct 2019View
  • Details of encumbrancesNon Encumbrance Certificate.pdf · uploaded 8 Oct 2019View
  • Copy of Layout Approval (in case of layout)Layout Copy.pdf · uploaded 8 Oct 2019View
  • Building Plan Approval / NA Order for plotted developmentBuilding Approval Plan.pdf · uploaded 8 Oct 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 8 Oct 2019View
  • Declaration in FORM BForm B - Declaration.pdf · uploaded 8 Oct 2019View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineer Certificate.pdf · uploaded 8 Oct 2019View
  • Proforma of Allotment letterGokul 3 - Draft Agreement for Sale.pdf · uploaded 8 Oct 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate.pdf · uploaded 9 Oct 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentG03 COMPLETION_v1.pdf · uploaded 24 Jan 2023View

Promoter documents

  • Legal Title reportTitle Report - Gokul 3.pdf · uploaded 8 Oct 2019View
  • Declaration Form BForm B - Declaration.pdf · uploaded 8 Oct 2019View

Technical documents

  • Layout ApprovalLayout Copy.pdfView
  • Building Plan ApprovalBuilding Approval Plan.pdfView

Proforma allotment letter

  • Proforma allotment letterGokul 3 - Draft Agreement for Sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No 40, Plot No 40

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Unit types
1BHK, Shop16 units in all
Address
Plot No 40, Survey No 130/2/1A 2/1B 2/1C 2/1D, Datta Mandir Road, Gangapur ShiwarPIN 422012
Village
Shivaji Nagar
Land area for this project
432 sq m (4,650 sq ft)
Permissible built-up area
499 sq m (5,375 sq ft)
Sanctioned built-up area
499 sq m (5,375 sq ft)
Designated bank account
City Union Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

Plot No 40Plot No 40Survey No 130/2/1A 2/1B 2/1C 2/1DSurvey No 130/2/1A 2/1B 2/1C 2/1D

Land as published on MahaRERA's project page

Plot No 40, Survey No 130/2/1A 2/1B 2/1C 2/1D

Boundaries

North
12 Mtr Colony Road
South
Survey No 130 1A
East
Plot No 39
West
40 Ft Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units · 0 parking spaces

16 units registered

1BHK · 12 unitsShop · 4 units
TypeCarpet areaUnits
1BHK33.03 sq m · 356 sq ft3
1BHK34.09 sq m · 367 sq ft3
1BHK34.21 sq m · 368 sq ft3
1BHK35.34 sq m · 380 sq ft3
Shop10.25 sq m · 110 sq ft1
Shop10.41 sq m · 112 sq ft1
Shop11.13 sq m · 120 sq ft1
Shop13.44 sq m · 145 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Gokul 3

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supply100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree Planting100%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage Water100%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShriniwas Consultant—
Chartered accountantJain Chhajed & Associates—
EngineerD B Gavhane—
OtherYash Pandurang Katale—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology