Gokul Infrastructure
Deedo IDDD-1GM1Of 4 registrations whose promised date has arrived, 4 kept it (100%).
Delivery record
None of 4 registrations with dates has moved or missed its RERA date
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gokul 1P51600007108 | Satpur | Completed | 31 Dec 2018 | — | On date |
| Gokul 3P51600022757 | Satpur | Completed | 30 Dec 2022 | — | On date |
| Gokul 5P51600031710 | Satpur | Certificate Signed | 31 Dec 2022 | 31 Dec 2022 | On date |
| Gokul 7P51600051838 | Satpur | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
Gokul Infrastructure, in questions
Does Gokul Infrastructure finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 4 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Gokul Infrastructure registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 4 completed on MahaRERA.
Does Gokul Infrastructure have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.