Skip to content
Residential / Group Housing · 2 buildings · 57 unitsRERA P51600023370

Vida 56

Deedo IDDP-NSK-4JJB

It is due for completion in Dec 2026, with no extension on record; no MahaRERA orders on record; 11% of its units are booked.

Nashik (M Corp.), Nashik 422005 · by Ananapurna Enterprises Partnership Firm & Other One

DeliveryDue Dec 2026No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales11% booked6 of 57 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Dec 2026, with no extension on record

  • This projectRegistered 12 Dec 2019, completion promised 6 Dec 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600023370
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160002337012 Dec 20196 Dec 20266 Dec 2026Ananapurna Enterprises Partnership Firm & Other OneProject page
Documents153

1 document held by Deedo, 152 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardANNPURNA ENTERPRISES.pdf · uploaded 30 Nov 2019Source

Legal

  • Legal Title report655 Nashik Title Report.pdf · uploaded 30 Nov 2019Source
  • Declaration Form BVida - 26 -Affidivit Cum Declaration.pdf · uploaded 30 Nov 2019Source
  • OtherCertificate.pdf · uploaded 9 Dec 2019Source

Migrated

  • 1 PAN CardANNPURNA ENTERPRISES.pdf · uploaded 30 Nov 2019Source
  • 1 Copy of the legal title report655 Nashik Title Report.pdf · uploaded 30 Nov 2019Source
  • 1 Details of encumbrancesENCUMBRANCES CERTIFICATE VIDA.pdf · uploaded 30 Nov 2019Source
Show all 153 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)655 (1)_page-0001 (1).pdf · uploaded 30 Nov 2019Source
  • 1 Building Plan Approval / NA Order for plotted development655 (1)_page-0001 (1).pdf · uploaded 30 Nov 2019Source
  • 1 Commencement Certificates / NA Order for plotted development655- Commencement Certificate.pdf · uploaded 30 Nov 2019Source
  • 1 Declaration in FORM BVida - 26 -Affidivit Cum Declaration.pdf · uploaded 30 Nov 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form - 1.pdf · uploaded 30 Nov 2019Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2.pdf · uploaded 30 Nov 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ananpurna Enterpirces - Thaker Vida26.pdf · uploaded 30 Nov 2019Source
  • 1 Proforma of Allotment letterVIDA RERA AGREEMENT TO SALE DRAFT.pdf · uploaded 30 Nov 2019Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)N M Thakker Thakker Vida26.pdf · uploaded 9 Dec 2019Source
  • 1 OtherCertificate.pdf · uploaded 9 Dec 2019Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Aug 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.pdf · uploaded 14 Aug 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-ANNAPURNA.pdf · uploaded 15 Aug 2021Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-NMT.pdf · uploaded 15 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5-ANNAPURNA.pdf · uploaded 17 Aug 2021Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5-NMT.pdf · uploaded 17 Aug 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 7 Oct 2021Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 7 Oct 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 Oct 2021Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 Oct 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.pdf · uploaded 7 Oct 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.pdf · uploaded 7 Oct 2021Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Annapurna.pdf · uploaded 7 Oct 2021Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 NMT.pdf · uploaded 7 Oct 2021Source
  • 3 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Annapurna.pdf · uploaded 7 Oct 2021Source
  • 4 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 NMT.pdf · uploaded 7 Oct 2021Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Mar 20.pdf · uploaded 7 Feb 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Jun 20.pdf · uploaded 7 Feb 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sept 20.pdf · uploaded 7 Feb 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 20.pdf · uploaded 7 Feb 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Mar 21.pdf · uploaded 7 Feb 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 21.pdf · uploaded 7 Feb 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Mar 22.pdf · uploaded 7 Feb 2023Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sept 22.pdf · uploaded 7 Feb 2023Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 22.pdf · uploaded 7 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)VIDA26_MAR_2020_c.pdf · uploaded 7 Feb 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)VIDA26_JUN_2020_c.pdf · uploaded 7 Feb 2023Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)VIDA26_SEP_2020_c.pdf · uploaded 7 Feb 2023Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)VIDA26_DEC_2020_c.pdf · uploaded 7 Feb 2023Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)VIDA26_MAR_2021_c.pdf · uploaded 7 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)VIDA26_DEC_2021_c.pdf · uploaded 7 Feb 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)VIDA26_MAR_2022_c.pdf · uploaded 7 Feb 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 26-DEC-2019.pdf · uploaded 14 Feb 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)DEC-2019.pdf · uploaded 14 Feb 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)MAR-2020.pdf · uploaded 14 Feb 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 26-MAR-2020.pdf · uploaded 14 Feb 2023Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 26-JUN-2020.pdf · uploaded 14 Feb 2023Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)JUNE-2020.pdf · uploaded 14 Feb 2023Source
  • 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)SEPT-2020.pdf · uploaded 14 Feb 2023Source
  • 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 26-SEPT-2020.pdf · uploaded 14 Feb 2023Source
  • 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 26-DEC-2020.pdf · uploaded 14 Feb 2023Source
  • 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)DEC-2020.pdf · uploaded 14 Feb 2023Source
  • 17 CA Certificate on Project Cost & Fund withdrawal (Form 3)MAR-2021.pdf · uploaded 14 Feb 2023Source
  • 18 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 26-MAR-2021.pdf · uploaded 14 Feb 2023Source
  • 19 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 26-DEC-2021.pdf · uploaded 14 Feb 2023Source
  • 20 CA Certificate on Project Cost & Fund withdrawal (Form 3)DEC-2021.pdf · uploaded 14 Feb 2023Source
  • 21 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA-56-MAR-2022.pdf · uploaded 14 Feb 2023Source
  • 22 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 56-MAR-2022.pdf · uploaded 14 Feb 2023Source
  • 23 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 56-JUN-2022.pdf · uploaded 14 Feb 2023Source
  • 24 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA-Form 3-JUN-2022.pdf · uploaded 14 Feb 2023Source
  • 25 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA-Form 3-SEPT-2022.pdf · uploaded 14 Feb 2023Source
  • 26 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 56-SEPT-2022.pdf · uploaded 14 Feb 2023Source
  • 27 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA 56-DEC-2022.pdf · uploaded 14 Feb 2023Source
  • 28 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIDA-Form 3-DEC-2022.pdf · uploaded 14 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5-MAR-2020.pdf · uploaded 14 Feb 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5.pdf · uploaded 14 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5-MAR-2022.pdf · uploaded 14 Feb 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5-JULY-2022.pdf · uploaded 14 Feb 2023Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Jun 22.pdf · uploaded 15 Feb 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)DEC-2019.pdf · uploaded 15 Feb 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)MAR-2020.pdf · uploaded 15 Feb 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)JUN-2020.pdf · uploaded 15 Feb 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)SEP-2020.pdf · uploaded 15 Feb 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)DEC-2020.pdf · uploaded 15 Feb 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)MAR-2021.pdf · uploaded 15 Feb 2023Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)DEC-2021.pdf · uploaded 15 Feb 2023Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)JUN-2022.pdf · uploaded 15 Feb 2023Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)SEP-2022.pdf · uploaded 15 Feb 2023Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)DEC-2022.pdf · uploaded 15 Feb 2023Source
  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Annapurna-VIDA-26-Form -2-Engineer Certificate- March-2022.pdf · uploaded 15 Feb 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Annapurna-Engi Cetificate-Form 2A-DEC-2019.pdf · uploaded 15 Feb 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)VIDA-26-Annapurna-Form 2A-Engineer Certificate-Dec-2022.pdf · uploaded 15 Feb 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)VIDA-26-Annapurna-Form 2A-Engineer Certificate-SEPT-2022.pdf · uploaded 15 Feb 2023Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Vida-26-Form 2A-Engineer Certificate-June-2022.pdf · uploaded 16 Feb 2023Source
  • 1 Declaration about Commencement CertificateS No 655-Nashik-Declaration about commencemnt certificate VIDA 56.pdf · uploaded 15 Mar 2023Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD DISCLOSURE ANNAPURNA ENTERPRISES.pdf · uploaded 15 Mar 2023Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD DISCLOSURE NM THAKKAR.pdf · uploaded 15 Mar 2023Source
  • 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 13 Jun 2023Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 13 Jun 2023Source
  • 29 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3.pdf · uploaded 13 Jun 2023Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)June-23.pdf · uploaded 31 Aug 2023Source
  • 17 Engineer’s Certificate on Cost Incurred on Project (Form 2)June-23.pdf · uploaded 31 Aug 2023Source
  • 30 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3 - Vida - 56.pdf · uploaded 31 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 VIDA ANNAPURNA.pdf · uploaded 27 Sep 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 VIDA THAKKER N M.pdf · uploaded 27 Sep 2023Source
  • 31 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VIDA CONSO 2023 09 30.pdf · uploaded 21 Nov 2023Source
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vida 26 - Form 1 - Architect Certificate.pdf · uploaded 7 Dec 2023Source
  • 18 Engineer’s Certificate on Cost Incurred on Project (Form 2)SEP-2023.pdf · uploaded 7 Dec 2023Source
  • 32 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VIDA CONSO 2023 12 31.pdf · uploaded 16 Jan 2024Source
  • 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)SNo655 Plot No389Architects Certificate DEC.pdf · uploaded 31 Jan 2024Source
  • 19 Engineer’s Certificate on Cost Incurred on Project (Form 2)DEC-2023.pdf · uploaded 14 Feb 2024Source
  • 33 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VIDA CONSO 2024 03 31.pdf · uploaded 21 May 2024Source
  • 20 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VIDA 2024 03 31_compressed.pdf · uploaded 3 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2-Form No 2A-Certificate No P51600023370 vida.pdf · uploaded 3 Jun 2024Source
  • 18 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vida 56-Aslam Kadri Architect Certificate -.pdf · uploaded 22 Jul 2024Source
  • 21 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 30-6-2024.pdf · uploaded 22 Jul 2024Source
  • 34 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 30 6 2024.pdf · uploaded 22 Jul 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VIDA CONSO 2024 09 30.pdf · uploaded 16 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 30 9 24 VIDA.pdf · uploaded 16 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VIDA CONSO 2024 12 31.pdf · uploaded 28 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VIDA 2024 12 31.pdf · uploaded 8 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VIDA 2024 12 31.pdf · uploaded 8 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 03 VIDA 2025 03 31.pdf · uploaded 19 Apr 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 VIDA ANNAPURNA 2024 03 31.pdf · uploaded 19 Apr 2025Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 VIDA THAKKER N M 2024 03 31.pdf · uploaded 19 Apr 2025Source
  • Form 5 (FY 2024-2025)Form 5 Final.pdf · uploaded 27 Nov 2025Source
  • Form 1Form 1.pdf · uploaded 4 Dec 2025Source
  • Form 2Form 2.pdf · uploaded 4 Dec 2025Source
  • Form 3Form 3.pdf · uploaded 4 Dec 2025Source
  • Disclosure of Sold and Booked InventoryVida 56-sold unsold.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 4 Dec 2025Source
  • Form 2A (FY 2024-2025)Form 2A.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 10 Mar 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 10 Mar 2026Source
  • Withdrawal Update Form 3Form 3_final.pdf · uploaded 10 Mar 2026Source
  • Withdrawal Update Form 1Form 1_11zon.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 2Form 2_11zon.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 3Form 3 _11zon.pdf · uploaded 12 May 2026Source
  • Form 2A (FY 2025-2026)Vida-56-Form2A-Engineering Certificate-dtd-31-03-2026.pdf · uploaded 6 Jul 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 30 Jul 2026Source

Technical

  • Document655 (1)_page-0001 (1).pdf · uploaded 30 Nov 2019Source
  • Document655 (1)_page-0001 (1).pdf · uploaded 30 Nov 2019Source

Technical (Architect)

  • DocumentFORM 1 VIDA 2024 12 31.pdf · uploaded 8 Feb 2025Source
  • DocumentFORM 1.pdf · uploaded 30 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 30 9 24 VIDA.pdf · uploaded 16 Oct 2024Source
  • DocumentFORM 2 VIDA 2024 12 31.pdf · uploaded 8 Feb 2025Source
  • DocumentForm 2.pdf · uploaded 30 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 655/1/1/5PLUS6/9/3PLUS4/C

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK57 units in all
Address
655/1/1/5PLUS6/9/3PLUS4/C, Gangapur Road, Pandit ColonyPIN 422005
Village
Nashik (M Corp.), Nashik taluka
Land area for this project
2,535 sq m (27,281 sq ft)
Permissible built-up area
8,110 sq m (87,300 sq ft)
Sanctioned built-up area
8,110 sq m (87,300 sq ft)
Designated bank account
88
Developed in phases
Yes

Survey, CTS, gat or plot numbers

655/1/1/5PLUS6/9/3PLUS4/C

Land as published on MahaRERA's project page

655/1/1/5PLUS6/9/3PLUS4/C

Boundaries

North
Plot 1 Oblic 7
South
S No 656
East
Plot 10 Plus 4 B
West
Plot 3 B Plus A

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking57 units

6 of 57 units booked (11%), as the promoter reported to MahaRERA

2BHK · 15 units3BHK · 42 units
BuildingTypeCarpet areaUnitsBooked
Building A2BHK81.72 sq m · 880 sq ft143
Building A3BHK32.56 sq m · 350 sq ft10
Building A3BHK115.9 sq m · 1,248 sq ft110
Building A3BHK130.98 sq m · 1,410 sq ft143
Building B2BHK81.72 sq m · 880 sq ft10
Building B3BHK98.42 sq m · 1,059 sq ft10
Building B3BHK115.9 sq m · 1,248 sq ft20
Building B3BHK130.98 sq m · 1,410 sq ft130

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMorphosis Architects—
ArchitectMorphosis Arch Morphosis Architects Old—
Chartered accountantAnand Rathi & Associates—
EngineerPrashant Patil—
EngineerSunil Ghodke—
OtherSelf—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Nashik (M Corp.)

All 1,251 projects in Nashik (M Corp.) · Compare Vida 56 with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology