Promised date passed7 floorsRERA P51600031399
Main building, Aditya Complex
Deedo IDDP-NSK-B7BD-ACMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked25%5 of 20 · MahaRERA
Completion31 Dec 2025as registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 36.5 m² (393 sq.ft) | 2 | 0 |
| 1BHK | 37.2 m² (401 sq.ft) | 2 | 0 |
| 1BHK | 38.3 m² (412 sq.ft) | 2 | 0 |
| 1BHK | 56.9 m² (612 sq.ft) | 2 | 0 |
| 2BHK | 76.5 m² (824 sq.ft) | 1 | 0 |
| 2BHK | 94.6 m² (1,018 sq.ft) | 1 | 0 |
| Office space | 71.1 m² (765 sq.ft) | 1 | 0 |
| Office space | 103.5 m² (1,114 sq.ft) | 1 | 0 |
| Shop | 8.6 m² (93 sq.ft) | 1 | 1 |
| Shop | 10.1 m² (109 sq.ft) | 1 | 0 |
| Shop | 10.5 m² (113 sq.ft) | 1 | 1 |
| Shop | 10.6 m² (114 sq.ft) | 1 | 1 |
| Shop | 10.7 m² (115 sq.ft) | 1 | 1 |
| Shop | 10.7 m² (115 sq.ft) | 1 | 1 |
| Shop | 25.4 m² (274 sq.ft) | 1 | 0 |
| Shop | 38.7 m² (416 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P51600031399 · registered 23 Oct 2021
- Promised completion
- 31 Dec 2025
- Revised completion
- 31 Dec 2025
- Sanctioned habitable floors
- 7
- Building
- ADITYA COMPLEX
- Sanctioned floors (incl. basement, stilt, podium)
- 7
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-NSK-B7BD-AC
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 31 Dec 2025.
How many floors does Main building have?
7 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology