Completed5 floorsRERA P51600004723
B Building, Deolali Meadows
Deedo IDDP-NSK-T3T5-BMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Completion31 Mar 20231 Dec 2021 · revised
Units & parking in B Building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Flats | 2,201.8 m² (23,700 sq.ft) | 37 | Not on record |
Parking: Closed/Covered 27 · Open Space 0 (as declared to MahaRERA)
Construction progress (declared)
Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
As registered with MahaRERA
- RERA registration
- P51600004723 · registered 9 Aug 2017
- Promised completion
- 1 Dec 2021
- Revised completion
- 31 Mar 2023
- Sanctioned habitable floors
- 5
- Deedo ID
- DP-NSK-T3T5-B
Questions about B Building
When is B Building due for completion?
The MahaRERA registration promises 1 Dec 2021, revised to 31 Mar 2023.
How many floors does B Building have?
5 sanctioned habitable floors, as registered with MahaRERA.
Data through11 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology