Skip to content
Residential / Group Housing · 4 buildings · 41 unitsRERA P51600004723

Deolali Meadows

Deedo IDDP-NSK-T3T5

MahaRERA shows it completed, after its date was pushed back 1 year and 3 months; no MahaRERA orders on record; 73% of its units are booked.

Deolali (Cb), Nashik 422401 · by Vaastu Realtors

DeliveryCompletedAs MahaRERA shows · after a 1 yr 3 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales73% booked30 of 41 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year and 3 months

  • This projectRegistered 9 Aug 2017, completion promised 1 Dec 2021, revised to 31 Mar 2023.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600004723
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000047239 Aug 20171 Dec 202131 Mar 2023Vaastu RealtorsProject page
Documents76

35 documents held by Deedo, 41 filings listed on MahaRERA's project page

Title report

Encumbrance details

Form 1 (4)

Allotment letter (3)

Show all 76 documentsShow fewer documents

Allotment letter (3)

Form B

Form 2 (4)

Form 5 (5)

Commencement certificate (3)

Form 2A

Registration certificate

Other (3)

Occupancy / completion certificate (2)

  • Occupancy / completion certificate31 Aug 2022ViewSource
  • Occupancy / completion certificate31 Aug 2022ViewSource

Extension certificate

Form 4

Layout plan

Building plan (3)

Document library

  • Building Plan Approval (IOD)BUILDING A (1).pdf · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)building b 1.pdf · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)Building b 2.pdf · uploaded 30 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Upload Architect Vaastu.pdf · uploaded 30 Jul 2017View
  • Copy of the legal title reportsearch report vastu.pdf · uploaded 30 Jul 2017View
  • Details of encumbrancesEncumbrances.pdf · uploaded 30 Jul 2017View
  • Copy of Layout Approval (in case of layout)declaration of layout.pdf · uploaded 30 Jul 2017View
  • Proforma of Allotment letterallotment letter.pdf · uploaded 30 Jul 2017View
  • Proforma of Allotment letterVaastu Draft1.pdf · uploaded 30 Jul 2017View
  • Proforma of Allotment letterVaastu Draft2.pdf · uploaded 30 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Enginners Certificate Vaastu.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BForm B Vaastu.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)VAASTU ENGINEERS CERTIFICATE 1ST QUATER.pdf · uploaded 31 Mar 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)vaastu architech certificare 1st quater compressed.pdf · uploaded 31 Mar 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)vaastu architech certificare 1st quater compressed.pdf · uploaded 31 Mar 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)vaastu architech certificate 2nd quater compressed.pdf · uploaded 31 Mar 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)VAASTU ENGINEERS CERTIFICATE 2ND QUATER.pdf · uploaded 31 Mar 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)arch certificate till 30 sept 2018(1).pdf · uploaded 29 Oct 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineers certificate till 30 sept 18.pdf · uploaded 29 Oct 2018View
  • Certificates of CA (Form 5)AUDIT REPORT.pdf · uploaded 31 Oct 2018View
  • Building Plan Approval (IOD)vaastu b building drawing.pdf · uploaded 27 Nov 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)RERA Audit Report Uploaded.pdf · uploaded 13 Nov 2019View
  • Commencement Certificates / NA Order for plotted developmentA Building Commensment certificate.pdf · uploaded 23 Dec 2019View
  • Commencement Certificates / NA Order for plotted developmentB Building commensment certificate.pdf · uploaded 23 Dec 2019View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quality Assurance Certificate 30092019.pdf · uploaded 4 Jan 2020View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA Audit Report_Singed_2019-20.pdf · uploaded 31 Dec 2020View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Vaastu Realtors FY20-21.pdf · uploaded 8 Aug 2022View
  • Declaration about Commencement CertificateRERA Format D.pdf · uploaded 27 Aug 2022View
  • Disclosure of sold/ booked inventorySold Unsold for RERA Extension.pdf · uploaded 27 Aug 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 31 Aug 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentcompletion certificate.pdf · uploaded 31 Aug 2022View
  • Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 29 Sep 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Annual Report on Statement of Ac 21-22 PSPH.pdf · uploaded 17 Oct 2022View

Promoter documents

  • Legal Title reportsearch report vastu.pdf · uploaded 30 Jul 2017View
  • Declaration Form BForm B Vaastu.pdf · uploaded 31 Jul 2017View

Technical documents

  • Building Plan ApprovalBUILDING A (1).pdfView
  • Building Plan Approvalbuilding b 1.pdfView
  • Building Plan ApprovalBuilding b 2.pdfView
  • Layout Approvaldeclaration of layout.pdfView
  • Building Plan Approvalvaastu b building drawing.pdfView

Proforma allotment letter

  • Proforma allotment letterVaastu Draft2.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 4, 5

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Unit types
Flats55 units in all
Address
Survey No.74 A and 74 B (Plot No. 3, 4, 5 and 7), Deolali (CB), Deolali (CB)PIN 422401
Village
Deolali (CB), Nashik taluka
Land area for this project
7,185 sq m (77,339 sq ft)
Permissible built-up area
3,672 sq m (39,526 sq ft)
Sanctioned built-up area
3,672 sq m (39,526 sq ft)
Recreational open space
2,531 sq m (27,243 sq ft)
Designated bank account
Union Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

457)74 B (Plot No. 3Survey No.74 A

Land as published on MahaRERA's project page

Survey No.74 A and 74 B (Plot No. 3, 4, 5 and 7)

Boundaries

North
Cantonment Road
South
Survey no 74E 74D
East
Cantonment Open Space
West
Part 08 74A and 74B

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking55 units · 45 parking spaces

55 units registered

Flats · 55 units
BuildingTypeCarpet areaUnits
A BuildingFlats1,470.3 sq m · 15,826 sq ft18
B BuildingFlats2,201.79 sq m · 23,700 sq ft37

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
A BuildingClosed/Covered000018
A BuildingOpen Space00000
B BuildingClosed/Covered000027
B BuildingOpen Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress3 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

A Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

B Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsConcrete road100%
  • Water SupplyCantonment water supply100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)chambersLines SepticTank100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingGarden100%
  • Street LightingAt Internal Roads100%
Show all 15 activitiesShow fewer activities
  • Community BuildingsClub House on Plot no.7100%
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceGarden100%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectChandrashekhar Chandankhede—
EngineerAchal Raje—
Real Estate AgentSandip Devidas Thakur—
Registered real estate agentSandipdevidas ThakurA51600006066

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology