Projects compared side by side
Deolali (Cb) · Nashik
Registration
RERA numbers
PromoterVaastu Realtors
Status on MahaRERACompleted
Registered on9 Aug 2017
Delivery
Promised completion1 Dec 2021
Revised completion31 Mar 2023
Delay vs RERA date+1 year and 3 monthsrevised completion date
Extension certificates1
Size
Project land area7,185 sq m
Buildings on record2
Units55
Units booked—
Regulatory
MahaRERA cases0
Documents on file35
Last checked on MahaRERA11 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology