Its promised completion date, Jun 2022, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.

Nanded Waghala (M Corp.), Nanded 431605 · by Kk Builders & Developers

Delivery4 yrs 5 mo past duePromised Jun 2022 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

Its promised completion date, Jun 2022, has passed and MahaRERA does not show it completed

  • This projectRegistered 5 Nov 2019, completion promised 30 Jun 2022, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51100022944
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P511000229445 Nov 201930 Jun 2022—Kk Builders & DevelopersProject page
Documents46

19 documents held by Deedo, 27 filings listed on MahaRERA's project page

Title report (4)

Form B

Form 2

Encumbrance details

Form 1

Show all 46 documentsShow fewer documents

Commencement certificate (3)

Registration certificate

Other (2)

Layout plan (3)

Building plan

Allotment letter

Document library

  • Declaration in FORM BForm B Declaration.pdf · uploaded 9 Oct 2019View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers certificate.pdf · uploaded 9 Oct 2019View
  • Building Plan Approval / NA Order for plotted developmentLayout Plan Shree Apartment.pdf · uploaded 9 Oct 2019View
  • Copy of Layout Approval (in case of layout)Building Permission Letter.pdf · uploaded 9 Oct 2019View
  • Copy of the legal title report7_12.pdf · uploaded 9 Oct 2019View
  • Copy of the legal title reportdevelopment Agreement_1.pdf · uploaded 9 Oct 2019View
  • Details of encumbrancesEncumbrance CERTIFICATE.pdf · uploaded 10 Oct 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect CERTIFICATE.pdf · uploaded 10 Oct 2019View
  • Copy of the legal title reportSale Deed of land.pdf · uploaded 10 Oct 2019View
  • Copy of the legal title reportSearch Report.pdf · uploaded 1 Nov 2019View
  • Copy of Layout Approval (in case of layout)lay out.pdf · uploaded 1 Nov 2019View
  • Copy of Layout Approval (in case of layout)Guntewari.pdf · uploaded 1 Nov 2019View
  • Commencement Certificates / NA Order for plotted developmentNA Order.pdf · uploaded 1 Nov 2019View
  • Proforma of Allotment letterBlank Format sale agreement and Allotment letter.pdf · uploaded 1 Nov 2019View
  • Commencement Certificates / NA Order for plotted developmentNA Order part 1-min.pdf · uploaded 4 Nov 2019View
  • Commencement Certificates / NA Order for plotted developmentNA Order part 2-min.pdf · uploaded 4 Nov 2019View
  • Commencement Certificates / NA Order for plotted developmentBuilding Permission Letter.pdf · uploaded 4 Nov 2019View

Promoter documents

  • Declaration Form BForm B Declaration.pdf · uploaded 9 Oct 2019View
  • Legal Title report7_12.pdf · uploaded 9 Oct 2019View
  • Legal Title reportdevelopment Agreement_1.pdf · uploaded 9 Oct 2019View
  • Legal Title reportSale Deed of land.pdf · uploaded 10 Oct 2019View
  • Legal Title reportSearch Report.pdf · uploaded 1 Nov 2019View

Technical documents

  • Building Plan ApprovalLayout Plan Shree Apartment.pdfView
  • Layout ApprovalBuilding Permission Letter.pdfView
  • Layout Approvallay out.pdfView
  • Layout ApprovalGuntewari.pdfView

Proforma allotment letter

  • Proforma allotment letterBlank Format sale agreement and Allotment letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPlot 42, Gut No. 123

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Unit types
1RK16 units in all
Address
Gut No. 123, Plot no. 42, Gut No. 123, Plot no 42, Taroda KhurdPIN 431605
Village
Nanded Waghala (M Corp.), Nanded taluka
Land area for this project
279 sq m (3,001 sq ft)
Permissible built-up area
303 sq m (3,257 sq ft)
Sanctioned built-up area
303 sq m (3,257 sq ft)
Designated bank account
Idbi Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

42Gut No. 123Plot no. 42

Land as published on MahaRERA's project page

Gut No. 123, Plot no. 42

Boundaries

North
Road 9mt wide
South
Property of Teachers Society
East
Plot No 41
West
Property of Anandrao Jadhav

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units · 1 parking space

16 units registered

1RK · 16 units
TypeCarpet areaUnits
1RK19.94 sq m · 215 sq ft4
1RK20.19 sq m · 217 sq ft4
1RK22.6 sq m · 243 sq ft4
1RK22.79 sq m · 245 sq ft4

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shri Apartment

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)10%
  • Plinth100%
  • Stilt Floor70%
  • Slabs of Super Structure40%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyIN PROGRESS0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)IN PROGRESS0%
  • Storm Water DrainsIN PROGRESS0%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterIN PROGRESS0%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingIN PROGRESS0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsIN PROGRESS0%
  • Electrical meter room, sub-station, receiving stationIN PROGRESS0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals54

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRajkumar G Ranvirkar—
ArchitectRajkumar G Ranvirkar—
ArchitectRajkumar G Ranvirkar—
ArchitectRajkumar G Ranvirkar—
ArchitectRajkumar G Ranvirkar—
ArchitectRajkumar G Ranvirkar—
ArchitectRajkumar G Ranvirkar—
ArchitectRajkumar G Ranvirkar—
Show all 54 professionalsShow fewer professionals
RoleNameRegistration no.
ArchitectRajkumar G Ranvirkar—
Chartered accountantCA Anand Dad—
Chartered accountantCA Anand Dad—
Chartered accountantCA Anand Dad—
Chartered accountantCA Anand Dad—
Chartered accountantCA Anand Dad—
Chartered accountantCA Anand Dad—
Chartered accountantCA Anand Dad—
Chartered accountantCA Anand Dad—
Chartered accountantCA Anand Dad—
EngineerShyam N Kadam—
EngineerShyam N Kadam—
EngineerShyam N Kadam—
EngineerShyam N Kadam—
EngineerShyam N Kadam—
EngineerShyam N Kadam—
EngineerShyam N Kadam—
EngineerShyam N Kadam—
EngineerShyam N Kadam—
OtherDevidas Gaikwad—
OtherDevidas Gaikwad—
OtherDevidas Gaikwad—
OtherDevidas Gaikwad—
OtherDevidas Gaikwad—
OtherDevidas Gaikwad—
OtherDevidas Gaikwad—
OtherDevidas Gaikwad—
OtherDevidas Gaikwad—
OtherParshuram Maroti Padalwar—
OtherParshuram Maroti Padalwar—
OtherParshuram Maroti Padalwar—
OtherParshuram Maroti Padalwar—
OtherParshuram Maroti Padalwar—
OtherParshuram Maroti Padalwar—
OtherParshuram Maroti Padalwar—
OtherParshuram Maroti Padalwar—
OtherParshuram Maroti Padalwar—
OtherPrakash Kundge—
OtherPrakash Kundge—
OtherPrakash Kundge—
OtherPrakash Kundge—
OtherPrakash Kundge—
OtherPrakash Kundge—
OtherPrakash Kundge—
OtherPrakash Kundge—
OtherPrakash Kundge—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology