Raj Park

Completed

Nanded Waghala (M Corp.), Nanded 431605 |Promoter: Mr Sanjay Balaprasad Biyani

Residential / Group HousingRERAP51100012601
6 Sep 2017Registered with MahaRERA
29 Oct 2019Promised completion
10Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
10
Land area for this project
10,044 sq m (1,08,114 sq ft)
Permissible built-up area
5,142 sq m (55,345 sq ft)
Sanctioned built-up area
4,118 sq m (44,323 sq ft)
Recreational open space
1,338 sq m (14,405 sq ft)
Address
P No 1 2 3p 4 5 6 7 8p 11 To 63PIN 431605
Designated bank account
The Shamrao Vithal Cooperative Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.08039, 72.84686
Raj Park is at latitude 19.08039, longitude 72.84686.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 29 Oct 2019

The latest completion date on record passed 7 years ago.

Registered
6 Sep 2017
Promised
29 Oct 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P511000126016 Sep 201729 Oct 2019—Mr Sanjay Balaprasad BiyaniProject page

10 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Galaxy A5—
Galaxy B5—
Galaxy C5—
Godavari3—
Kaweri Lane3—
Krishna Lane3—
Saraswati East3—
Saraswati West3—
Yamuna Lane A3—
Yamuna Lane B3—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Galaxy AClosed/Covered000015
Galaxy AOpen Space000010
Galaxy BClosed/Covered000010
Galaxy BOpen Space00006
Galaxy CClosed/Covered00008
Galaxy COpen Space00005
GodavariClosed/Covered00005
GodavariOpen Space00000
Kaweri LaneClosed/Covered000012
Kaweri LaneOpen Space00000
Krishna LaneClosed/Covered00005
Krishna LaneOpen Space00000
Saraswati EastClosed/Covered00008
Saraswati EastOpen Space00000
Saraswati WestClosed/Covered00008
Saraswati WestOpen Space00000
Yamuna Lane AClosed/Covered00004
Yamuna Lane AOpen Space00004
Yamuna Lane BClosed/Covered00004
Yamuna Lane BOpen Space00004

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Galaxy A

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises90%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Galaxy B

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
  • Sanitary Fittings within the flats / premises90%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Galaxy C

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure20%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Godavari

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Kaweri Lane

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Krishna Lane

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Saraswati East

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Saraswati West

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Yamuna Lane A

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Yamuna Lane B

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsCOMPLEITED100%
  • Water SupplyCOMPLEITED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEWERAGE LINE100%
  • Storm Water DrainsCORPORATION LINE CONNECTION BUILDING PENDING100%
  • Landscaping & Tree PlantingCOMPLEITED100%
  • Street LightingCOMPLEITED100%
  • Community BuildingsROW HOUSE100%
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalWORK IN PROGRESS50%
  • Water conservation /Rain water harvestingBORE WEEL100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsWORK NOT STARTED0%
  • Electrical meter room, sub-station, receiving stationWORK IN PROGRESS85%
  • Aggregate area of recreational Open SpaceLAND OF CENTER10%
  • Open ParkingWORK IN PROGRESS80%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

12 documents held by Deedo, 16 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title report007.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)007.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted development007.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)00.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM Bimagetopdf(6).pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesUntitled-9.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterimagetopdf(5).pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)imagetopdf(3).pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)imagetopdf(4).pdf · uploaded 31 Jul 2017View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentRAJ PARK -compressed.pdf · uploaded 14 Jan 2020View
  • Architect’s Certificate on Completion of Project (Form 4)RAJ PARK -compressed.pdf · uploaded 14 Jan 2020View

Promoter documents

  • Legal Title report007.pdf · uploaded 31 Jul 2017View
  • Declaration Form Bimagetopdf(6).pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout Approval007.pdfView
  • Building Plan Approval00.pdfView

Proforma allotment letter

  • Proforma allotment letterimagetopdf(5).pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nanded Waghala (M Corp.), Nanded taluka

Survey, CTS, gat or plot numbers

P NO 1 2 3P 4 5 6 7 8P 11 TO 63

As published on MahaRERA's project page

P NO 1 2 3P 4 5 6 7 8P 11 TO 63

Boundaries

North
Pandan Road
South
Morge And Korde
East
Land Op Gnajaji
West
Nanded Malegoan Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Ganesh S More—
ArchitectAr Ganesh S More—
ArchitectAr Ganesh S More—
ArchitectAr Ganesh S More—
EngineerRavindra Bhabhulay—
EngineerRavindra Bhabhulay—
EngineerRavindra Bhabhulay—
EngineerRavindra Bhabhulay—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology