Completed7 floorsRERA P51100015354
Krishna, Raghunath Nagar
Deedo IDDP-NAN-05CS-KRISHNMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Completion30 Dec 2023as registered
Units & parking in Krishna
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 27.3 m² (294 sq.ft) | 2 | Not on record |
| 1BHK | 32.5 m² (350 sq.ft) | 2 | Not on record |
| 1BHK | 33.2 m² (357 sq.ft) | 4 | Not on record |
| 1BHK | 35.2 m² (379 sq.ft) | 4 | Not on record |
| 1BHK | 35.3 m² (380 sq.ft) | 8 | Not on record |
| 1BHK | 36.4 m² (392 sq.ft) | 2 | Not on record |
| 1BHK | 37.4 m² (403 sq.ft) | 2 | Not on record |
| 1BHK | 39.7 m² (428 sq.ft) | 4 | Not on record |
| 2BHK | 41.8 m² (450 sq.ft) | 4 | Not on record |
| 2BHK | 52.7 m² (568 sq.ft) | 2 | Not on record |
| 2BHK | 53.2 m² (573 sq.ft) | 4 | Not on record |
| 2BHK | 55.7 m² (600 sq.ft) | 2 | Not on record |
| SHOP 1 8 | 11.2 m² (120 sq.ft) | 2 | Not on record |
| SHOP 2 7 | 11 m² (118 sq.ft) | 2 | Not on record |
| SHOP 3 6 | 8.8 m² (95 sq.ft) | 2 | Not on record |
| SHOP 4 5 | 11 m² (118 sq.ft) | 2 | Not on record |
Parking: Closed/Covered 30 · Open Space 0 (as declared to MahaRERA)
Construction progress (declared)
Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
As registered with MahaRERA
- Sanctioned habitable floors
- 7
- Deedo ID
- DP-NAN-05CS-KRISHN
Questions about Krishna
When is Krishna due for completion?
The MahaRERA registration promises 30 Dec 2023.
How many floors does Krishna have?
7 sanctioned habitable floors, as registered with MahaRERA.
Data through10 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology