Main building, Anant Enclave
Deedo IDDP-NAN-V2V6-AE36 of 43 flats are unsold and 7 are booked, per MahaRERA's Oct 2026 disclosure; no sale deed is on record yet.
Every flat, floor by floor
Tap a flat to see its record.
- Booked, no deed yet
- Unsold
Flat number not read (2): no floor on record and the number doesn't say one.
Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
Flat 702
715 sq ft · floor 7
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Main building
MahaRERA's project page with unit types hasn't been imported for this registration.
Parking: Closed/Covered 58 · Open Space 0 (as declared to MahaRERA)
Construction progress (declared)
Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.
- Excavation100%
- Basement (if any)0%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
- Sanitary Fittings within the flats / premises20%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
As registered with MahaRERA
- Sanctioned habitable floors
- 6
- Also named
- Anant Enclave
- Deedo ID
- DP-NAN-V2V6-AE
Questions about Main building
How many flats in Main building are sold?
0 flats have a sale on record, 7 are booked without a sale deed yet and 36 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
When is Main building due for completion?
The MahaRERA registration promises 31 Dec 2027.
How many floors does Main building have?
6 sanctioned habitable floors, as registered with MahaRERA.