RERA projects in Nanded

104 projects under 108 MahaRERA registrations across 10 localities, registered 2017–2026. 3% have a completion date extended beyond the one promised.

District
104RERA projectsin 10 localities
108Registrationssome projects hold several
39Completion still due53 past their completion date, 10 marked completed
12 monthsMedian extension beyond promised date3% of registrations extended
10Regulatory caseson 8 projects
262Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201722
20185
20192
20207
20214
20226
202313
202417
202510
20266

Projects in Nanded

104 projects registered with MahaRERA in this district and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Padmanabha ResidencyShree Samarth Builders And DevelopersP5110005570415 Apr 202431 Dec 2029—Not yet due0
Gvc Gangadham SkyilaGvc DevelopersP511000554752 Apr 202431 Dec 2028—Not yet due0
Ramanuj AUttam Kishanrao BacchewarP511000555672 Apr 202431 Dec 2028—Not yet due0
Prayagraj AmsdevelopersP5110005539722 Mar 202430 Jun 2026—Promised date passed0
A R Khiyani CityM B Builders And DevelopersP5110005504526 Feb 202431 Oct 2027—Not yet due0
Gvc Siddhi SkyparkSidhi DevelopersP5110005496221 Feb 202431 Mar 2028—Not yet due0
Kamal ResidencyAkruti ConstructionsP5110005429415 Jan 202430 May 2026—Promised date passed0
Gvc Saptagiri SignatureGvc DevelopersP5110005193113 Jul 202331 Dec 2026—Not yet due0
Nabhangan ParkRamchandra Bhagwanrao DeshmukhP5110005104322 May 202331 Dec 2027—Not yet due0
Vrandawan ApartmentVisava DevelopersP5110005099619 May 202330 Dec 2025—Promised date passed0
Padmavati NagariJyoti Deepak PujariP5110005089115 May 202331 Mar 2028—Not yet due0
Bharadiya TowerRaj AssociatesP5110005069428 Apr 20234 Aug 2025—Promised date passed0
Shri Swami Samarth HeightsShri Swami Samarth EstatesP5110005065121 Apr 202331 Mar 2027—Not yet due0
Samartha ApartmentSatish Bhanudasrao MoreP5110005048717 Apr 20231 Aug 2028—Not yet due0
Krishna Kunj ResidencyShri Krishna BuildersP511000503705 Apr 202320 Feb 2026—Promised date passed0
Krushna KunjShri BuilderP511000500396 Mar 20234 Aug 2025—Promised date passed0
Omkar AppartmentDivyaamrit Constructions India Pvt LtdP511000500166 Mar 20231 Jan 2026—Promised date passed0
Anaika HeightsDarak DevelopersP5110004965522 Feb 202331 Dec 2027—Not yet due0
Infinate OneMayuresh Govind BodkeP511000492463 Feb 202331 Dec 2025—Promised date passed0
Amrit MallDivyaamrit Constructions India Pvt LtdP5110004911730 Jan 202331 Dec 2028—Not yet due0
Gvc Shagun CityShagun BuildconP51100047425, P5110004781631 Oct 202231 Dec 2025—Promised date passed0
Anusaya HeightsAnusaya HeightsP5110004607715 Jun 202230 Sep 2022—Promised date passed0
Krupasindhu ArcadeKrupasindhu PropertiesP5110004565726 May 202231 Mar 2028—Not yet due0
Krushna Nilayam ApartmentOsr InfrastructureP5110003456911 Apr 202231 Mar 2024—Promised date passed0
RenukaR K Builders & DevelopersP5110003460411 Apr 202231 Dec 2024—Promised date passed0

Localities in Nanded

By number of registered projects, as MahaRERA names them.

Other districts

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Gvc Developers5 projects
  2. Mr Sanjay Balaprasad Biyani5 projects
  3. msdevelopers4 projects
  4. Pharande Developers3 projects
  5. R K Builders & Developers3 projects
  6. Divyaamrit Constructions India Pvt Ltd2 projects
  7. Jyoti Deepak Pujari2 projects
  8. Krupasindhu Properties2 projects
  9. OSR Infrastructure2 projects
  10. Padmavati Developers2 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology