Deedo IDDP-NAN-0JM1Its promised completion date, May 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 5% of its units are booked.
Wadi Bk., Nanded 431604 · by Akruti Constructions
Buying a flat here?
See every deed registered on it.
Its promised completion date, May 2026, has passed and MahaRERA does not show it completed
- This projectRegistered 15 Jan 2024, completion promised 30 May 2026, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Main buildingSize not on record22% booked
- Tower A6 floors · 32 units9% booked
- Tower B5 floors · 30 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51100054294
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51100054294 | 15 Jan 2024 | 30 May 2026 | 30 May 2026 | Akruti Constructions | Project page |
Documents62
2 documents held by Deedo, 60 filings listed on MahaRERA's project page
Show all 62 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted development1DEBADWAR 2sheet-Model Layout.pdf · uploaded 8 Jun 2023Source
- 2 Building Plan Approval / NA Order for plotted development2DEBADWAR 2sheet-Model Layout_11zon.pdf · uploaded 8 Jun 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 8 Jun 2023Source
- 1 a Details of encumbrances concerned to FinanceNon encumbrances certificate legal.pdf · uploaded 9 Sep 2023Source
- 1 b Details of encumbrances concerned to LegalNon encumbrances certificate legal.pdf · uploaded 9 Sep 2023Source
- 1 Declaration about Commencement CertificateFormat D declaration of commencement certificate.pdf · uploaded 9 Sep 2023Source
- 1 CERSAI detailsUndertaking of no security interest.pdf · uploaded 9 Sep 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organisation.pdf · uploaded 9 Sep 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate bank account including non - encumbrance.pdf · uploaded 9 Sep 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation Report.pdf · uploaded 9 Sep 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report.pdf · uploaded 9 Sep 2023Source
- 1 Copy of the legal title reportLegal Title Report_11zon.pdf · uploaded 20 Sep 2023Source
- 1 Proforma of Allotment letterAllotment Letter_11zon.pdf · uploaded 20 Sep 2023Source
- 1 Proforma of Agreement for saleAgreement To Sale.pdf · uploaded 20 Sep 2023Source
- 1 Declaration in FORM Bdeclaration-supported-by-an-affidavit-which-shall-be-signed-by-the-promoter-or-any-person-authorized-by-the-promoter-form-b_11zon.pdf · uploaded 6 Oct 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3- Akruti Constructions Revised_11zon.pdf · uploaded 18 Oct 2023Source
- 1 Other – TechnicalWhatsApp PDF.pdf · uploaded 12 Jan 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)self certification akruti.pdf · uploaded 18 May 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)self certification akruti.pdf · uploaded 18 May 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality assurance (kamal residency).pdf · uploaded 18 May 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)self certification akruti.pdf · uploaded 18 May 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 17 Oct 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-01.pdf · uploaded 17 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_11zon.pdf · uploaded 17 Oct 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-03_11zon.pdf · uploaded 17 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 17 Oct 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-02.pdf · uploaded 17 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5.pdf · uploaded 17 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_001.pdf · uploaded 1 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 engineer's certificate.pdf · uploaded 1 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's certificate.pdf · uploaded 5 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineering certificate.pdf · uploaded 24 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3.pdf · uploaded 26 Apr 2025Source
- DocumentArchitect's certificate.pdf · uploaded 29 Apr 2025Source
- Form 5 (FY 2024-2025)Form 5 Akruti Construction.pdf · uploaded 1 Aug 2025Source
- Form 1Architect certificate .pdf · uploaded 5 Aug 2025Source
- Form 2Form 2.pdf · uploaded 5 Aug 2025Source
- Form 3Form 3 AK.pdf · uploaded 5 Aug 2025Source
- Disclosure of Sold and Booked InventoryDisclouser of Sold Booked Inventroy.pdf · uploaded 5 Aug 2025View
Technical
- Document1DEBADWAR 2sheet-Model Layout.pdf · uploaded 8 Jun 2023Source
- Document2DEBADWAR 2sheet-Model Layout_11zon.pdf · uploaded 8 Jun 2023Source
- Document1DEBADWAR 2sheet-Model Layout.pdf · uploaded 8 Jun 2023Source
- Document2DEBADWAR 2sheet-Model Layout_11zon.pdf · uploaded 8 Jun 2023Source
- Other – TechnicalWhatsApp PDF.pdf · uploaded 12 Jan 2024Source
Technical (Architect)
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel GUT NO 108
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK62 units in all
- Address
- Gut No 108, Mauje Kautha, Nanded, Mauje Kautha, NandedPIN 431604
- Village
- Nanded Waghala (M Corp.), Nanded taluka
- Land area for this project
- 2,000 sq m (21,528 sq ft)
- Permissible built-up area
- 6,399 sq m (68,880 sq ft)
- Sanctioned built-up area
- 6,399 sq m (68,880 sq ft)
- Designated bank account
- 109
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
GUT NO 108, MAUJE KAUTHA, NANDED
Boundaries
- North
- Land In Gut No 229 Of Munjajirao Kale
- South
- 30 Ft Wide Road
- East
- Remaining Land Of Owner
- West
- Land Of Rekha Anil Sharma
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking62 units
3 of 62 units booked (5%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Tower A | 2BHK | 65.72 sq m · 707 sq ft | 5 | 0 |
| Tower A | 2BHK | 67.19 sq m · 723 sq ft | 5 | 0 |
| Tower A | 2BHK | 69.63 sq m · 749 sq ft | 5 | 0 |
| Tower A | 2BHK | 72.11 sq m · 776 sq ft | 5 | 1 |
| Tower A | 3BHK | 82.72 sq m · 890 sq ft | 5 | 1 |
| Tower A | 3BHK | 86.18 sq m · 928 sq ft | 5 | 1 |
| Tower A | 3BHK | 104.02 sq m · 1,120 sq ft | 1 | 0 |
| Tower A | 3BHK | 110.93 sq m · 1,194 sq ft | 1 | 0 |
Show all 14 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Tower B | 2BHK | 65.34 sq m · 703 sq ft | 5 | 0 |
| Tower B | 2BHK | 65.68 sq m · 707 sq ft | 5 | 0 |
| Tower B | 2BHK | 67.38 sq m · 725 sq ft | 5 | 0 |
| Tower B | 2BHK | 70.52 sq m · 759 sq ft | 5 | 0 |
| Tower B | 2BHK | 73.19 sq m · 788 sq ft | 5 | 0 |
| Tower B | 2BHK | 73.72 sq m · 794 sq ft | 5 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Kiran Dembani | — |
| Architect | Riken Doshi | — |
| Chartered accountant | Ca Mayur Praful Agrawal | — |
| Chartered accountant | Yash P Agrawal | — |
| Engineer | K V Amrutwad | — |
Source: MahaRERA project page. Contact details are not shown.