Skip to content
Deedo home
Menu

Krishnum Nagari-IV

Completion date passed

Rui, Nagpur 441108 |Promoter: Alliance Hariom Infrastructure

21 Aug 2020Registered with MahaRERA
28 Feb 2026Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

MahaRERA's search listing gives this project's name, promoter and location only.

MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 28 Feb 2026

The latest completion date on record passed 8 months ago.

Registered
21 Aug 2020
Promised
28 Feb 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050002613321 Aug 202028 Feb 2026—Alliance Hariom InfrastructureProject page

Documents

1 document held by Deedo

Registration certificate

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Rui

Survey, CTS, gat or plot numbers

KH 36/2A OF MAUZA RUIP.H.NO 41

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology