Alliance Hariom Infrastructure

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Krishnum Nagari-IVP50500026133Rui2020Certificate Signed28 Feb 202628 Jun 2026+4 months
Krishnum Nagari VP50500028146Nagpur (Rural)2021Certificate Signed17 Jun 202617 Oct 2026+4 months
Krishnum Nagari -6P50500049546Gotal Panjari2023Certificate Signed31 Oct 202729 Feb 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Krishnum Nagari-IV+4 mo
  • Krishnum Nagari V+4 mo
  • Krishnum Nagari -6+4 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Krishnum Nagari-IV (P50500026133).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.