RERA projects in Rengapar

9 projects under 9 MahaRERA registrations, registered 2017–2025. 44% have a completion date extended beyond the one promised.

Locality
9RERA projects
9Registrations
5Completion still due4 past their completion date, 1 marked completed
4 monthsMedian extension beyond promised date44% of registrations extended
0Regulatory casesnone on MahaRERA's lists
29Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20180
20190
20200
20210
20222
20232
20241
20252

Projects in Rengapar

9 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Varadlakshmi Heights-1M/S Innovative IndustriesP505000787077 Jan 202531 Dec 202731 Dec 2027Not yet due0
Devashree HeightsG & D Constructions And DevelopersP505000786751 Jan 202530 Sep 202630 Jan 2027Extended 4 mo0
Friends MallFriends InfraP5050007716129 Jul 202431 Mar 202731 Jul 2027Extended 4 mo0
Dollar ResidenceSalma Akil SayyadP5050005355410 Nov 202330 Apr 202530 Apr 2025Promised date passed0
Durvansh NagarDurvansh Builders And DevelopersP5050004975624 Feb 202331 Mar 202831 Jul 2028Extended 4 mo0
Prime 9 ApartmentsSanjay Vishweshwarpuri BhagweP5050003415124 Mar 20221 May 20231 May 2023Promised date passed0
Kaavya EnclaveAditya InfrastructureP5050003385614 Mar 202230 Jun 202430 Jun 2024Promised date passed0
Imperial HeightsImperial Gruh Nirman Sahakari SansthaP505000129427 Sep 201730 Dec 202331 Dec 2035Extended 144 mo0
City Centre - 2Badjate Real EstatesP505000038696 Aug 201731 Jul 2022—Completed0

Other localities in Nagpur (Rural)

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Aditya Infrastructure1 project
  2. Badjate Real Estates1 project
  3. Durvansh Builders And Developers1 project
  4. Friends Infra1 project
  5. G & D Constructions And Developers1 project
  6. Imperial Gruh Nirman Sahakari Sanstha1 project
  7. M/S Innovative Industries1 project
  8. Salma Akil Sayyad1 project
  9. Sanjay Vishweshwarpuri Bhagwe1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology