City Centre - 2

Completed

Rengapar, Nagpur 441122 |Promoter: Badjate Real Estates

6 Aug 2017Registered with MahaRERA
31 Jul 2022Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Completed
Buildings
1
Land area for this project
6,144 sq m (66,133 sq ft)
Permissible built-up area
9,216 sq m (99,200 sq ft)
Sanctioned built-up area
2,182 sq m (23,490 sq ft)
Address
X-102-2, Midc, MidcPIN 441122
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.50831, 73.79087
City Centre - 2 is at latitude 18.50831, longitude 73.79087.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Jul 2022

The latest completion date on record passed 4 years and 3 months ago.

Registered
6 Aug 2017
Promised
31 Jul 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P505000038696 Aug 201731 Jul 2022—Badjate Real EstatesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
City Centre - 25—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000086
Open Space000026

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

City Centre - 2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCOMMON100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)COMMON100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingCOMMON100%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCOMMON100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsCOMMON100%
  • Electrical meter room, sub-station, receiving stationCOMMON100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open Parking26 COMMON100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

59 documents held by Deedo, 72 filings listed on MahaRERA's project page

Titles

Encumbrance

Form 2s

Allotment letters

Form b

Form 1s

Commencement certificate

Registration certificate

Form 2as

Form 5s

Completion

Form 4

Others

Layout plan

Building plans

Document library

  • Building Plan Approval (IOD)sanctioned.pdf · uploaded 29 Jul 2017View
  • Building Plan Approval (IOD)Building Permit-ilovepdf-compressed.pdf · uploaded 29 Jul 2017View
  • Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 29 Jul 2017View
  • Copy of the legal title reporttitle deed part1.pdf · uploaded 29 Jul 2017View
  • Copy of the legal title reporttitle deed part 2.pdf · uploaded 29 Jul 2017View
  • Copy of the legal title reporttitle deed 3.pdf · uploaded 29 Jul 2017View
  • Details of encumbrancesencumbrances.pdf · uploaded 29 Jul 2017View
  • Copy of Layout Approval (in case of layout)layout.pdf · uploaded 29 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer.pdf · uploaded 29 Jul 2017View
  • Proforma of Allotment letteragrement to sale.pdf · uploaded 29 Jul 2017View
  • Declaration in FORM Baffidavit.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect cert.pdf · uploaded 31 Jul 2017View
  • OtherPROPOSED TYPICAL FLOOR PLAN.PDF · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentcomencment certificate.pdf · uploaded 25 Apr 2018View
  • Building Plan Approval (IOD)p01.pdf · uploaded 25 Apr 2018View
  • Building Plan Approval (IOD)p02.pdf · uploaded 25 Apr 2018View
  • Building Plan Approval (IOD)p03.pdf · uploaded 25 Apr 2018View
  • Building Plan Approval (IOD)p04.pdf · uploaded 25 Apr 2018View
  • Building Plan Approval (IOD)Revised Sanctioned map with sign BAdjate Real-ilovepdf-compressed-1-2.pdf · uploaded 19 Jul 2018View
  • Building Plan Approval (IOD)Revised Sanctioned 3.pdf · uploaded 19 Jul 2018View
  • Building Plan Approval (IOD)Revised Sanctioned 4.pdf · uploaded 19 Jul 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE JUNE-21_20210827_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Badjate June-21_20210828_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCITECT CERTIFICATE MARCH-21_20210827_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Badjate March-21_20210828_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCITECT CERTIFICATE DECEMBER-20_20210827_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Badjate December-20_20210828_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE SEPTEMBER-20_20210827_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE JUNE-20_20210827_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Badjate September-20_20210828_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Badjate June-20_20210828_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects certificate ended on 31-3-2020_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate End 31-March-20_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate end 31-december-19_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate end on 30-september-2019_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate End December-2019_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate end 30-June-2019_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate End 30-September-2019_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate End 30-June-2019_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate end 31-March-2019_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate end 31-March-2019_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate End on 31-March-2018_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate end 31-March-2018_20210805_0001.pdf · uploaded 11 Sep 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate 30 Sept 2021.pdf · uploaded 26 Apr 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate 31 Mar 2022.pdf · uploaded 26 Apr 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Architect Certificate 30 Dec 2021.pdf · uploaded 26 Apr 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A Mar 21.pdf · uploaded 26 Apr 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Mar 22.pdf · uploaded 26 Apr 2023View
  • Architect’s Certificate on Completion of Project (Form 4)Architect cerificate Completion of Project .pdf · uploaded 26 Apr 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 02 Sep.pdf · uploaded 26 Apr 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate.pdf · uploaded 26 Apr 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 02 Dec.pdf · uploaded 26 Apr 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 02.pdf · uploaded 26 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CA CERTIFICATE ANNUAL REPORT 2.pdf · uploaded 26 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)CA CERTIFICATE ANNUAL REPORT .pdf · uploaded 26 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 05.pdf · uploaded 26 Apr 2023View

Promoter documents

  • Legal Title reporttitle deed part1.pdf · uploaded 29 Jul 2017View
  • Legal Title reporttitle deed part 2.pdf · uploaded 29 Jul 2017View
  • Legal Title reporttitle deed 3.pdf · uploaded 29 Jul 2017View
  • Declaration Form Baffidavit.pdf · uploaded 31 Jul 2017View

Technical documents

  • Building Plan Approvalsanctioned.pdfView
  • Building Plan ApprovalBuilding Permit-ilovepdf-compressed.pdfView
  • Layout Approvallayout.pdfView
  • Building Plan Approvalp01.pdfView
  • Building Plan Approvalp02.pdfView
  • Building Plan Approvalp03.pdfView
  • Building Plan Approvalp04.pdfView
  • Building Plan ApprovalRevised Sanctioned map with sign BAdjate Real-ilovepdf-compressed-1-2.pdfView
  • Building Plan ApprovalRevised Sanctioned 3.pdfView
  • Building Plan ApprovalRevised Sanctioned 4.pdfView

Other legal documents

  • OtherPROPOSED TYPICAL FLOOR PLAN.PDFView

Proforma allotment letter

  • Proforma allotment letterALLOTMENT LETTER.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Rengapar, Nagpur (Rural) taluka

Survey, CTS, gat or plot numbers

X1022

As published on MahaRERA's project page

X-102-2

Boundaries

North
Road
South
X-102-4
East
X-102-3
West
X-102-1

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectBhavik Jain—
ArchitectKapil P Thakur—
ArchitectNL Bose—
Chartered accountantAgrawal Saraf & Associates—
EngineerRajesh Shashtrakar—

Source: MahaRERA project page. Contact details are not shown.