Galaxy Park
Deedo IDDP-NGP-V4KEIts promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 38% of its units are booked.
Ranala, Nagpur 441401 · by Shakti Builders And Developers
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 21 Aug 2023, completion promised 30 Jun 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP50500052403
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500052403 | 21 Aug 2023 | 30 Jun 2025 | 30 Jun 2025 | Shakti Builders And Developers | Project page |
Documents180
59 documents held by Deedo, 121 filings listed on MahaRERA's project page
Show all 180 documentsShow fewer documents
Other (21)
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedView
- OtherDate not statedView
- OtherDate not statedView
Encumbrance details (3)
Commencement certificate (2)
Form 1 (18)
- Form 1Date not statedViewSource
- Form 1Date not statedViewSource
- Form 1Date not statedViewSource
- Form 1Date not statedViewSource
- Form 1Date not statedViewSource
- Form 1Date not statedViewSource
- Form 1Date not statedViewSource
- Form 1Date not statedViewSource
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
Form 2 (7)
Allotment letter (2)
Finance
- Other – FinanceForm 3 (1).pdf · uploaded 9 Aug 2023View
Legal
Migrated
- 1 PAN CardPAN CARD.pdf · uploaded 5 Jul 2023View
- 1 Copy of the legal title reportFormat A.pdf · uploaded 5 Jul 2023View
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 5 Jul 2023View
- 1 Declaration in FORM BFORM B.pdf · uploaded 7 Jul 2023View
- 1 CERSAI detailsCERSAI_Search_Report_200273559799_For_Asset_Based_Search_05_07_2023_18_14_12_803.pdf · uploaded 7 Jul 2023View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM3.pdf · uploaded 7 Jul 2023View
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK ACCOUNT FORMAT A (ON LETTER HEAD).pdf · uploaded 7 Jul 2023View
- 1 Deviation Report with respect to Allotment letterDeviation Allotment Plots.pdf · uploaded 7 Jul 2023View
- 1 a Details of encumbrances concerned to FinanceNONECUM FINANCIAL (ON FIRMS LETTER HEAD).pdf · uploaded 8 Jul 2023View
- 2 a Details of encumbrances concerned to FinanceNON ECUMBRANCE LEGAL (ON FIRMS LETTER HEAD).pdf · uploaded 8 Jul 2023View
- 1 b Details of encumbrances concerned to LegalNONECUM FINANCIAL (ON FIRMS LETTER HEAD).pdf · uploaded 8 Jul 2023View
- 2 b Details of encumbrances concerned to LegalNON ECUMBRANCE LEGAL (ON FIRMS LETTER HEAD).pdf · uploaded 8 Jul 2023View
- 1 Copy of Layout Approval (in case of layout)11zon_IMAGES-to-PDF (9)_11zon.pdf · uploaded 8 Jul 2023View
- 1 Building Plan Approval / NA Order for plotted development11zon_IMAGES-to-PDF (9)_11zon.pdf · uploaded 8 Jul 2023View
- 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate fom nmdra_compressed.pdf · uploaded 8 Jul 2023View
- 1 Declaration about Commencement CertificateDeclaration About Commencement Certificate.pdf · uploaded 8 Jul 2023View
- 1 Proforma of Agreement for saleAgreement for sell Plot.pdf · uploaded 8 Jul 2023View
- 1 Proforma of Allotment letterAllotment Letter Plot.pdf · uploaded 8 Jul 2023View
- 2 CERSAI detailsCERSAI Declaration.pdf · uploaded 12 Jul 2023View
- 1 Deviation Report with respect to model copy of AgreementDeviation ATS Apartment.pdf · uploaded 12 Jul 2023View
- 1 Other – FinanceForm 3 (1).pdf · uploaded 9 Aug 2023View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)ENGG CERTIFICATE_11zon.pdf · uploaded 19 Oct 2023View
- 1 Disclosure of sold/ booked inventoryInventory Disclosure - Promoter Letterhead.pdf · uploaded 19 Oct 2023View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT FORM 1.pdf · uploaded 3 Feb 2024View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG FORM 2.pdf · uploaded 3 Feb 2024View
- 2 Disclosure of sold/ booked inventoryInventory Disclosure.pdf · uploaded 3 Feb 2024View
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH FORM-1.pdf · uploaded 6 May 2024View
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG FORM-2.pdf · uploaded 6 May 2024View
- 3 Disclosure of sold/ booked inventoryInventory Disclosure - Promoter Letterhead.pdf · uploaded 6 May 2024View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Shakti builders.pdf · uploaded 6 May 2024View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 CA SHAKTI.pdf · uploaded 9 May 2024View
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH FORM-1.pdf · uploaded 27 Jul 2024View
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG FORM-2.pdf · uploaded 27 Jul 2024View
- 4 Disclosure of sold/ booked inventoryInventory Disclosure - 18.pdf · uploaded 27 Jul 2024View
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM-3.pdf · uploaded 27 Jul 2024View
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q12425.pdf · uploaded 7 Oct 2024View
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q22425.pdf · uploaded 7 Oct 2024View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q42324.pdf · uploaded 7 Oct 2024View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q32324.pdf · uploaded 7 Oct 2024View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q22324.pdf · uploaded 7 Oct 2024View
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Q32324.pdf · uploaded 9 Oct 2024View
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Q42324.pdf · uploaded 9 Oct 2024View
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Q12425.pdf · uploaded 9 Oct 2024View
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Q22425.pdf · uploaded 9 Oct 2024View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Q22324.pdf · uploaded 9 Oct 2024View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineer Q22324.pdf · uploaded 9 Oct 2024View
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineer Q32324.pdf · uploaded 9 Oct 2024View
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineer Q42324.pdf · uploaded 9 Oct 2024View
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineer Q12425.pdf · uploaded 9 Oct 2024View
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineer Q22425.pdf · uploaded 9 Oct 2024View
- 1 Disclosure of sold/ booked inventoryInventory Disclosure - Q22324 (1).pdf · uploaded 9 Oct 2024View
- 2 Disclosure of sold/ booked inventoryInventory Disclosure - Q32324 (1).pdf · uploaded 9 Oct 2024View
- 3 Disclosure of sold/ booked inventoryInventory Disclosure - Q42324 (1).pdf · uploaded 9 Oct 2024View
- 4 Disclosure of sold/ booked inventoryInventory Disclosure - Q12425 (1).pdf · uploaded 9 Oct 2024View
- 5 Disclosure of sold/ booked inventoryInventory Disclosure - Q22425 (1).pdf · uploaded 9 Oct 2024View
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q32425.pdf · uploaded 8 Nov 2024View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 SHAKTI (1).pdf · uploaded 11 Nov 2024View
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (1).pdf · uploaded 13 Nov 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (10) (1).pdf · uploaded 13 Nov 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)6 Architect’s Certificate of Percentage of Completion of Work (Form 1) (6) (1).pdf · uploaded 13 Nov 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)7 Architect’s Certificate of Percentage of Completion of Work (Form 1) (5) (1).pdf · uploaded 13 Nov 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)8 Architect’s Certificate of Percentage of Completion of Work (Form 1) (5) (1).pdf · uploaded 13 Nov 2024Source
- Form 5 (FY 2023-2024)FORM 5 SHAKTI.pdf · uploaded 28 May 2025Source
- Form 1ARCH FORM-1.pdf · uploaded 31 May 2025Source
- Form 2ENGG FORM-2.pdf · uploaded 31 May 2025Source
- Form 3FORM-3 CA SHAKTI.pdf · uploaded 31 May 2025Source
- Disclosure of Sold and Booked InventoryInventory Disclosure - Promoter Letterhead.pdf · uploaded 31 May 2025Source
- Form 1ARCHITECT FORM 1.pdf · uploaded 2 Jun 2025Source
- Form 1ARCH RANALA LAYOUT RERA.pdf · uploaded 2 Jun 2025Source
- Form 1ARCH FORM-1.pdf · uploaded 2 Jun 2025Source
- Form 2ENGG FORM 2.pdf · uploaded 2 Jun 2025Source
- Form 2ENGG CERTIFICATE_11zon.pdf · uploaded 2 Jun 2025Source
- Form 2Form 2 - Engineer Q12425.pdf · uploaded 2 Jun 2025Source
- Form 3FORM-3.pdf · uploaded 2 Jun 2025Source
- Form 3FORM-3.pdf · uploaded 2 Jun 2025Source
- Form 3CA FORM-3.pdf · uploaded 2 Jun 2025Source
- Disclosure of Sold and Booked InventoryInventory Disclosure.pdf · uploaded 2 Jun 2025Source
- Disclosure of Sold and Booked InventoryInventory Disclosure - Promoter Letterhead.pdf · uploaded 2 Jun 2025Source
- Disclosure of Sold and Booked InventoryInventory Disclosure - 18.pdf · uploaded 2 Jun 2025Source
Technical
- Document11zon_IMAGES-to-PDF (9)_11zon.pdf · uploaded 8 Jul 2023View
- Document11zon_IMAGES-to-PDF (9)_11zon.pdf · uploaded 8 Jul 2023View
- OthersForm 3 Q32324.pdf · uploaded 4 Oct 2024Source
- OthersForm 3 Q22324.pdf · uploaded 4 Oct 2024Source
- OthersForm 3 Q42324.pdf · uploaded 4 Oct 2024Source
- OthersForm 3 Q12425.pdf · uploaded 4 Oct 2024Source
- OthersForm 3 Q22425.pdf · uploaded 4 Oct 2024Source
- OthersInventory Disclosure - Q42324.pdf · uploaded 4 Oct 2024Source
- OthersInventory Disclosure - Q32324.pdf · uploaded 4 Oct 2024Source
- OthersInventory Disclosure - Q22425.pdf · uploaded 4 Oct 2024Source
- OthersInventory Disclosure - Q22324.pdf · uploaded 4 Oct 2024Source
- OthersInventory Disclosure - Q12425.pdf · uploaded 4 Oct 2024Source
- OthersForm 1 - Architect Q42324.pdf · uploaded 4 Oct 2024Source
- OthersForm 1 - Architect Q32324.pdf · uploaded 4 Oct 2024Source
- OthersForm 1 - Architect Q22425.pdf · uploaded 4 Oct 2024Source
- OthersForm 1 - Architect Q22324.pdf · uploaded 4 Oct 2024Source
- OthersForm 1 - Architect Q12425.pdf · uploaded 4 Oct 2024Source
- OthersForm 2 - Engineer Q42324.pdf · uploaded 4 Oct 2024Source
- OthersForm 2 - Engineer Q32324.pdf · uploaded 4 Oct 2024Source
- OthersForm 2 - Engineer Q22425.pdf · uploaded 4 Oct 2024Source
- OthersForm 2 - Engineer Q22324.pdf · uploaded 4 Oct 2024Source
- OthersForm 2 - Engineer Q12425.pdf · uploaded 4 Oct 2024Source
Technical (Architect)
- DocumentForm 1.pdf · uploaded 27 Sep 2024Source
- DocumentForm 1 - Architect Q22324.pdf · uploaded 9 Oct 2024View
- DocumentForm 1 - Architect Q32324.pdf · uploaded 9 Oct 2024View
- DocumentForm 1 - Architect Q42324.pdf · uploaded 9 Oct 2024View
- DocumentForm 1 - Architect Q12425.pdf · uploaded 9 Oct 2024View
- DocumentForm 1 - Architect Q22425.pdf · uploaded 9 Oct 2024View
- Document4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (1).pdf · uploaded 13 Nov 2024Source
- Document5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (10) (1).pdf · uploaded 13 Nov 2024Source
- Document6 Architect’s Certificate of Percentage of Completion of Work (Form 1) (6) (1).pdf · uploaded 13 Nov 2024Source
- Document7 Architect’s Certificate of Percentage of Completion of Work (Form 1) (5) (1).pdf · uploaded 13 Nov 2024Source
- Document8 Architect’s Certificate of Percentage of Completion of Work (Form 1) (5) (1).pdf · uploaded 13 Nov 2024Source
Technical (Engineer)
- Documentform 2.pdf · uploaded 27 Sep 2024Source
- DocumentForm 2 - Engineer Q22324.pdf · uploaded 9 Oct 2024View
- DocumentForm 2 - Engineer Q32324.pdf · uploaded 9 Oct 2024View
- DocumentForm 2 - Engineer Q42324.pdf · uploaded 9 Oct 2024View
- DocumentForm 2 - Engineer Q12425.pdf · uploaded 9 Oct 2024View
- DocumentForm 2 - Engineer Q22425.pdf · uploaded 9 Oct 2024View
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel KHASRA 115/1B BHOGWATADAR CLASS 1 RIGHTS OF WAY MOUZA RANALA
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- Khasra 115/1b Bhogwatadar Class 1 Rights Of Way Mouza Ranala, Khasra No 115/1/B Bhogwatdar Class 1 Rights Mouza Ranala, KampteePIN 441401
- Village
- Ranala, Kamptee taluka
- Land area for this project
- 12,093 sq m (1,30,169 sq ft)
- Permissible built-up area
- 5,989 sq m (64,468 sq ft)
- Sanctioned built-up area
- 5,989 sq m (64,468 sq ft)
- Recreational open space
- 1,189 sq m (12,799 sq ft)
- Designated bank account
- 119
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
KHASRA 115/1B BHOGWATADAR CLASS 1 RIGHTS OF WAY MOUZA RANALA
Boundaries
- North
- Khasra No 123 125 126 127
- South
- Khasra No 115 1a 2 3 4a 4b
- East
- Road
- West
- Khasra No 115 1 A 2 3 4a 4b
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Lokesh Kadu | — |
| Chartered accountant | CA Murtuza Hussain Holawala | — |
| Engineer | Lokesh Kadu | — |
Source: MahaRERA project page. Contact details are not shown.