RERA projects in Kamptee
125 projects under 126 MahaRERA registrations, registered 2017–2026. 4% have a completion date extended beyond the one promised.
Taluka
125RERA projects
126Registrationssome projects hold several
66Completion still due46 past their completion date, 6 marked completed
23 monthsMedian extension beyond promised date4% of registrations extended
1Regulatory caseson 1 project
160Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 3 |
| 2018 | 7 |
| 2019 | 7 |
| 2020 | 3 |
| 2021 | 6 |
| 2022 | 10 |
| 2023 | 20 |
| 2024 | 27 |
| 2025 | 16 |
| 2026 | 13 |
Projects in Kamptee
125 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mahalaxmi Nagar -54 (Sector-2)Mahalaxmi Aedificators Private Limited | PP1190002602125 | 5 Oct 2026 | 4 Sep 2031 | — | Not yet due | 0 |
| Govind Nagri 2Shree Balaji Land Developers | PP1190002602070 | 1 Oct 2026 | 31 Mar 2029 | — | Not yet due | 0 |
| Shri Shyam City 2Yogesh Shamrao Makde | PP1190002602089 | 1 Oct 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Dev ResidencyShree Taj Construction, Matoshree Prabha Builders & Developers | PR1190002602018 | 23 Sep 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Rana GreensRana Greens | PP1190002601848 | 9 Sep 2026 | 31 Dec 2027 | — | Not yet due | 0 |
| Shri Gopal KrishnaDnyaneshwar Krishnaji Padole | PP1190002601799 | 7 Sep 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Karmabhoomi-2Karmabhoomi | PP1191012601682 | 27 Aug 2026 | 31 Mar 2031 | — | Not yet due | 0 |
| Galaxy Park 4Shakti Builders And Developers | PR1190002601314 | 27 Jul 2026 | 30 Jun 2029 | — | Not yet due | 0 |
| Salasar ComplexSalasar Builders and Developers | PM1190002600775 | 15 Jun 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Shubh Laxmi RealtorsShubh Laxmi Realtors | PP1190002600448 | 17 May 2026 | 31 Mar 2031 | — | Not yet due | 0 |
| Mahalaxmi Nagar- 47Mahalaxmi Aedificators Private Limited | PP1190002600006 | 6 Apr 2026 | 30 Dec 2030 | — | Not yet due | 0 |
| Rudransh CityMaruti Real Estate | PP1190002502384 | 17 Feb 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Jais Industrial ParkkSubhashchandra Dayaram Jais | PP1190002501989 | 6 Jan 2026 | 31 Mar 2028 | — | Not yet due | 0 |
| Kesar Vihar 2Kesar India Limited | PP1190002501855 | 23 Dec 2025 | 31 Oct 2026 | — | Not yet due | 0 |
| Ashoka ImperialAshoka Imperial | PP1190002501804 | 16 Dec 2025 | 31 Dec 2032 | — | Not yet due | 0 |
| Gurunanak Enclave KhairiJasmeetsingh Bhatia and Mandeepsingh Bhatia | PP1190002501607 | 28 Nov 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Mahalaxmi Nagar 44 & Goverdhan Nagari 14Harode Infrastructures | PP1190002501286 | 20 Oct 2025 | 31 May 2030 | — | Not yet due | 0 |
| Icon ResidencyAnjum Saher Sayed Iqbal | PP1190002501151 | 9 Oct 2025 | 30 Jun 2027 | — | Not yet due | 0 |
| AyodhyaAyodhya Mukunda Keshavam | PP1191012500733 | 10 Sep 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| Shree EliteShree Builders And Land Developers | PR1190002500712 | 4 Sep 2025 | 15 Aug 2028 | — | Not yet due | 0 |
| Kesar Gold VillasKesar IM Infra Projects | PP1190002500461 | 4 Aug 2025 | 31 Oct 2026 | — | Not yet due | 0 |
| Kp Nagar 2Kp Developers And Builders | PP1190002500235 | 8 Jul 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Mahakali Greens-2Sandeep Manoharrao Bawankar & Tushar Manoharrao Bawankar | P50500080787 | 7 Jul 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| D P Nagar 1M/s D P Developers & Builders | PP1190002500207 | 4 Jul 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Swastik Industrial ParkShri. Ashish S Chhangani & Smt. Preeti V Chhangani | P50500080775 | 4 Jul 2025 | 14 Feb 2028 | — | Not yet due | 0 |
Other talukas in Nagpur
Most active promoters
By projects registered here, as named on MahaRERA.
- Harode Infrastructures3 projects
- Kesar India Limited3 projects
- Kesar Infracon Private Limited3 projects
- Mahalaxmi Aedificators Private Limited3 projects
- Rupali Pramod Gharde3 projects
- Hba Construction Company Pvt.ltd2 projects
- Jasmeetsingh Amarjeetsingh Bhatia2 projects
- Karmabhoomi2 projects
- Kp Developers And Builders2 projects
- Maitreya Developers2 projects
Data through12 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology