RERA projects in Kalameshwar
19 projects under 19 MahaRERA registrations, registered 2017–2026. 58% have a completion date extended beyond the one promised.
Taluka
19RERA projects
19Registrations
11Completion still due8 past their completion date, 1 marked completed
4 monthsMedian extension beyond promised date58% of registrations extended
0Regulatory casesnone on MahaRERA's lists
20Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 0 |
| 2019 | 1 |
| 2020 | 3 |
| 2021 | 1 |
| 2022 | 1 |
| 2023 | 2 |
| 2024 | 2 |
| 2025 | 3 |
| 2026 | 4 |
Projects in Kalameshwar
19 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Bhagyalaxmi PrimeSaubhagyasarita Reality LLP | PR1190002601236 | 20 Jul 2026 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
| Ram Nagar 7Ashish Ramraoji Bobade | PP1190002601091 | 8 Jul 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Manik Nagari Dream CityUnique Associate Infra Developers | PP1190002502515 | 26 Feb 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Ashadeep EnclaveAshadeep Builders and Developers | PR1190002502098 | 16 Jan 2026 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| SDPL SuvarnabhumiSandeep Dwellers Pvt. Ltd. | PP1190002501173 | 10 Oct 2025 | 30 Sep 2032 | 30 Jan 2033 | Extended 4 mo | 0 |
| Maya Nagari Park 2Pravin Wamanrao Bhoyar | P50500080425 | 4 Jun 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Aarav ResidencyBhu Nivesh Pariwar | P50500078901 | 20 Jan 2025 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Dera Greens 3Narayan Chandiram Demble | P50500077813 | 7 Nov 2024 | 31 Dec 2035 | 30 Apr 2036 | Extended 4 mo | 0 |
| Mahalaxmi NagarChandrashekhar Baburao Kale | P50500055314 | 14 Mar 2024 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| SangamKailas Deonathji Gurao And Rajendra Vinayak Bahe | P50500052334 | 14 Aug 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Maya Nagari Park-1Pravin Wamanrao Bhoyar | P50500050710 | 28 Apr 2023 | 31 Dec 2024 | 31 Dec 2026 | Extended 24 mo | 0 |
| 14 Mile Industrial And Logistic ParkTrue Value Land Developers | P50500047523 | 7 Nov 2022 | 15 Aug 2024 | 15 Aug 2024 | Promised date passed | 0 |
| Bhagirath MangalamShrigopal Rameshkumar Sales Private Limited | P50500028230 | 18 Feb 2021 | 30 Dec 2023 | 7 Jan 2025 | Extended 13 mo | 0 |
| Gajanan Nagar Thorane LayoutVanita Thorane & Sneha Thorane | P50500025481 | 6 Jun 2020 | 30 Sep 2022 | 30 Sep 2022 | Promised date passed | 0 |
| Gajanan PrideYogesh Rajendra Pali & Shilpa Yogesh Pali | P50500024654 | 26 Feb 2020 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| Shivaji ComplexAdditya Infrastructure | P50500024491 | 18 Feb 2020 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| Surya NagariSurya Buildcon & Developers | P50500019330 | 23 Jan 2019 | 30 Jun 2019 | 30 Jun 2019 | Promised date passed | 0 |
| Vidarbha Premier Nagri Phase 3 KalmeshwarPrakash Narayanrao Raole | P50500010477 | 31 Aug 2017 | 31 Dec 2018 | 30 Oct 2020 | Completed | 0 |
| Kasturi AppartmentsSky Developers And Promoters India Pvt. Ltd. | P50500000856 | 23 Jul 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
Other talukas in Nagpur
Most active promoters
By projects registered here, as named on MahaRERA.
- Pravin Wamanrao Bhoyar2 projects
- Additya Infrastructure1 project
- Ashadeep Builders and Developers1 project
- Ashish Ramraoji Bobade1 project
- Bhu Nivesh Pariwar1 project
- Chandrashekhar Baburao Kale1 project
- Kailas Deonathji Gurao And Rajendra Vinayak Bahe1 project
- Narayan Chandiram Demble1 project
- Prakash Narayanrao Raole1 project
- Sandeep Dwellers Pvt. Ltd.1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology