RERA projects in Ramtek

7 projects under 7 MahaRERA registrations, registered 2017–2025. 33% have a completion date extended beyond the one promised.

Taluka
7RERA projects
7Registrations
2Completion still due4 past their completion date, 1 marked completed
20 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20180
20191
20201
20210
20220
20230
20240
20251

Projects in Ramtek

7 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Deshmukh ComplexRajendra DeshmukhPM11900025010591 Oct 202531 Dec 202830 Apr 2029Extended 4 mo0
Nostalgia VillasSanjay Bhagwandas GangwaniP5050002509518 Mar 202030 Dec 202430 Dec 2024Promised date passed0
White Tiger And Wild FlowerMilindkumar Bhaurao MeshramP505000222909 Sep 201930 Dec 202331 Dec 2026Extended 36 mo0
Mahakali NagarUsha Ravindra SethiyaP505000145218 Dec 201731 Dec 201931 Dec 2019Promised date passed0
Mahakali NagarSanjay Manoharrao BobdeP505000144724 Dec 201731 Dec 201931 Dec 2019Promised date passed0
Mahakali NagarGaju Baburao BisaneP505000139772 Nov 201731 Dec 2019—Completed0
P50500048804P50500048804————0

Other talukas in Nagpur

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Gaju Baburao Bisane1 project
  2. Milindkumar Bhaurao Meshram1 project
  3. Rajendra Deshmukh1 project
  4. Sanjay Bhagwandas Gangwani1 project
  5. Sanjay Manoharrao Bobde1 project
  6. Usha Ravindra Sethiya1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology