Skip to content
Deedo home
Menu

Shakti Builders And Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Galaxy ParkP50500052403Ranala2023Certificate Signed30 Jun 202530 Jun 2025On date
Galaxy Park 4PR1190002601314Bhilgaon2026Not reported30 Jun 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Galaxy ParkOn date
  • Galaxy Park 4On date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology