Ruby
Deedo IDDP-NGP-H5H7MahaRERA shows it completed; no MahaRERA orders on record; 82% of its units are booked.
Nagpur (M Corp.), Nagpur 440030 · by Leverage Realtors Private Limited · 100% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 6 Sep 2018, completion promised 30 Mar 2024.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
6 buildings
Open a building to see every flat, floor by floor.
- Block A7 floors · 28 units100% booked
- Block B7 floors · 28 units86% booked
- Block C7 floors · 22 units100% booked
- Block D7 floors · 22 units100% booked
- Block E7 floors · 48 units100% booked
- Block F7 floors · 48 units35% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP50500017717
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500017717 | 6 Sep 2018 | 30 Mar 2024 | 30 Mar 2024 | Leverage Realtors Private Limited | Project page |
Documents90
37 documents held by Deedo, 53 filings listed on MahaRERA's project page
Other (6)
Layout plan (9)
- Layout planDate not statedView
Show all 90 documentsShow fewer documents
Layout plan (9)
Commencement certificate
- Commencement certificateDate not statedView
Form 1 (5)
Title report
- Title reportDate not statedView
Encumbrance details
- Encumbrance detailsDate not statedView
Building plan (11)
- Building planDate not statedView
- Building planDate not statedView
- Building planDate not statedView
- Building planDate not statedView
- Building planDate not statedView
- Building planDate not statedView
- Building planDate not statedView
- Building planDate not statedView
- Building planDate not statedView
- Building planDate not statedView
- Building planDate not statedView
Form B
- Form BDate not statedView
Form 2
- Form 2Date not statedView
Legal
Migrated
- 1 PAN CardPan Card- LRPL.pdf · uploaded 27 Aug 2018View
- 1 Copy of the legal title reportSearch Report.pdf · uploaded 27 Aug 2018View
- 1 Details of encumbrancesEncumbrace Certificate.pdf · uploaded 27 Aug 2018View
- 1 Copy of Layout Approval (in case of layout)Layout Map.pdf · uploaded 27 Aug 2018View
- 1 Building Plan Approval (IOD)Map 1.pdf · uploaded 27 Aug 2018View
- 2 Building Plan Approval (IOD)Map 2.pdf · uploaded 27 Aug 2018View
- 3 Building Plan Approval (IOD)Map 3.pdf · uploaded 27 Aug 2018View
- 4 Building Plan Approval (IOD)Map 4.pdf · uploaded 27 Aug 2018View
- 5 Building Plan Approval (IOD)Map 5.pdf · uploaded 27 Aug 2018View
- 6 Building Plan Approval (IOD)Map 6.pdf · uploaded 27 Aug 2018View
- 7 Building Plan Approval (IOD)Map 7.pdf · uploaded 27 Aug 2018View
- 8 Building Plan Approval (IOD)Map 8.pdf · uploaded 27 Aug 2018View
- 9 Building Plan Approval (IOD)Map 9.pdf · uploaded 27 Aug 2018View
- 10 Building Plan Approval (IOD)Map 10.pdf · uploaded 27 Aug 2018View
- 11 Building Plan Approval (IOD)Map 11.pdf · uploaded 27 Aug 2018View
- 1 Commencement Certificates / NA Order for plotted developmentBuilding Permit.pdf · uploaded 27 Aug 2018View
- 1 Declaration in FORM BAffidavit.pdf · uploaded 27 Aug 2018View
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 27 Aug 2018View
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 27 Aug 2018View
- 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 27 Aug 2018View
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 27 Aug 2018View
- 2 Proforma of Allotment lettersample agreement final.pdf · uploaded 27 Aug 2018View
- 1 OtherRelease Letter.pdf · uploaded 27 Aug 2018View
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ruby Architect Certificate_compressed.pdf · uploaded 25 Aug 2021View
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate.pdf · uploaded 2 Mar 2022View
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate Ruby Block CD.pdf · uploaded 12 Dec 2022View
- 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentArchitect CertificateRuby CD.pdf · uploaded 12 Dec 2022View
- 4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate- Wing-F.pdf · uploaded 17 Oct 2023View
- 2 OtherFORM 4 ALL.pdf · uploaded 28 Oct 2023View
- 5 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentArchitect's Certificate- Ruby F.pdf · uploaded 15 Dec 2023View
- 13 Architect’s Certificate on Completion of Project (Form 4)Form 4 Ruby_Completion of all Block (1).pdf · uploaded 15 Dec 2023View
- 14 Architect’s Certificate on Completion of Project (Form 4)Architect's Certificate- Ruby F.pdf · uploaded 15 Dec 2023View
- 15 Architect’s Certificate on Completion of Project (Form 4)3 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for plotted development.pdf · uploaded 15 Dec 2023View
- 2 Certificates of CA (Form 3)CA Certificate LRPL.pdf · uploaded 13 Mar 2024View
- 6 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate Shops.pdf · uploaded 2 Apr 2024View
Technical
- DocumentLayout Map.pdf · uploaded 27 Aug 2018View
- DocumentMap 1.pdf · uploaded 27 Aug 2018View
- DocumentMap 2.pdf · uploaded 27 Aug 2018View
- DocumentMap 3.pdf · uploaded 27 Aug 2018View
- DocumentMap 4.pdf · uploaded 27 Aug 2018View
- DocumentMap 5.pdf · uploaded 27 Aug 2018View
- DocumentMap 6.pdf · uploaded 27 Aug 2018View
- DocumentMap 7.pdf · uploaded 27 Aug 2018View
- DocumentMap 8.pdf · uploaded 27 Aug 2018View
- DocumentMap 9.pdf · uploaded 27 Aug 2018View
- DocumentMap 10.pdf · uploaded 27 Aug 2018View
- DocumentMap 11.pdf · uploaded 27 Aug 2018View
Technical (Architect)
- DocumentRuby Architect Certificate_compressed.pdf · uploaded 25 Aug 2021View
Technical (Engineer)
- DocumentEngineers Certificate.pdf · uploaded 27 Aug 2018View
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 149/1 PART, KH NO 149/4
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2 BHK, Shop, 2BHK, 1.5 BHK, 1 BHK196 units in all
- Address
- Plot No 2, Kh No 149/4 And 149/1 Part, Mouza Nara, Nagpur, NagpurPIN 440030
- Village
- Nagpur (M Corp.), Nagpur (Urban) taluka
- Location
- 21.14580, 79.08815
- Land area for this project
- 5,821 sq m (62,656 sq ft)
- Permissible built-up area
- 10,652 sq m (1,14,654 sq ft)
- Sanctioned built-up area
- 8,952 sq m (96,355 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO 2, KH NO 149/4 AND 149/1 PART, MOUZA NARA
Boundaries
- North
- Kh No 149
- South
- Kh No 148
- East
- Kh No 149
- West
- 12 Mtr Road And Open Space
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking196 units
161 of 196 units booked (82%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Block A | 2 BHK | 50.3 sq m · 541 sq ft | 20 | 20 |
| Block A | 2 BHK | 53.46 sq m · 575 sq ft | 2 | 2 |
| Block A | 2 BHK | 53.82 sq m · 579 sq ft | 1 | 1 |
| Block A | 2 BHK | 59.59 sq m · 641 sq ft | 1 | 1 |
| Block A | Shop | 11.53 sq m · 124 sq ft | 1 | 1 |
| Block A | Shop | 28.69 sq m · 309 sq ft | 2 | 2 |
| Block A | Shop | 34.63 sq m · 373 sq ft | 1 | 1 |
| Block B | 2BHK | 50.3 sq m · 541 sq ft | 20 | 20 |
Show all 30 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Block B | 2BHK | 53.45 sq m · 575 sq ft | 3 | 3 |
| Block B | 2BHK | 59.59 sq m · 641 sq ft | 1 | 1 |
| Block B | Shop | 11.53 sq m · 124 sq ft | 1 | 0 |
| Block B | Shop | 28.69 sq m · 309 sq ft | 2 | 0 |
| Block B | Shop | 34.62 sq m · 373 sq ft | 1 | 0 |
| Block C | 2 BHK | 50.3 sq m · 541 sq ft | 10 | 10 |
| Block C | 2 BHK | 53.46 sq m · 575 sq ft | 1 | 1 |
| Block C | 2 BHK | 53.82 sq m · 579 sq ft | 1 | 1 |
| Block C | 2 BHK | 55.51 sq m · 598 sq ft | 8 | 8 |
| Block C | 2 BHK | 58.69 sq m · 632 sq ft | 1 | 1 |
| Block C | 2 BHK | 59.59 sq m · 641 sq ft | 1 | 1 |
| Block D | 2 BHK | 50.3 sq m · 541 sq ft | 10 | 10 |
| Block D | 2 BHK | 53.46 sq m · 575 sq ft | 2 | 2 |
| Block D | 2 BHK | 55.51 sq m · 598 sq ft | 8 | 8 |
| Block D | 2 BHK | 58.67 sq m · 632 sq ft | 1 | 1 |
| Block D | 2 BHK | 59.59 sq m · 641 sq ft | 1 | 1 |
| Block E | 1.5 BHK | 33.51 sq m · 361 sq ft | 23 | 23 |
| Block E | 1.5 BHK | 33.79 sq m · 364 sq ft | 1 | 1 |
| Block E | 1 BHK | 29.06 sq m · 313 sq ft | 24 | 24 |
| Block F | 1.5 BHK | 33.52 sq m · 361 sq ft | 22 | 10 |
| Block F | 1.5 BHK | 33.85 sq m · 364 sq ft | 2 | 2 |
| Block F | 1 BHK | 29.05 sq m · 313 sq ft | 24 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Prashant Baliram Satpute | — |
| Registered real estate agent | Jyoti Ranjan Pani | — |
Source: MahaRERA project page. Contact details are not shown.