Promised date passed7 floorsRERA P50500017717
Block B, Ruby
Deedo IDDP-NGP-H5H7-BMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked86%24 of 28 · MahaRERA
Completion30 Mar 2024as registered
Units & parking in Block B
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 50.3 m² (541 sq.ft) | 20 | 20 |
| 2BHK | 53.5 m² (575 sq.ft) | 3 | 3 |
| 2BHK | 59.6 m² (641 sq.ft) | 1 | 1 |
| Shop | 11.5 m² (124 sq.ft) | 1 | 0 |
| Shop | 28.7 m² (309 sq.ft) | 2 | 0 |
| Shop | 34.6 m² (373 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P50500017717 · registered 6 Sep 2018
- Promised completion
- 30 Mar 2024
- Revised completion
- 30 Mar 2024
- Sanctioned habitable floors
- 7
- Sanctioned floors (incl. basement, stilt, podium)
- 7
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-NGP-H5H7-B
Questions about Block B
When is Block B due for completion?
The MahaRERA registration promises 30 Mar 2024.
How many floors does Block B have?
7 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology