Leverage Realtors Private Limited

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
OnyxP50500013820Nagpur (M Corp.)2017Certificate Signed28 Nov 202128 Nov 2021On date
RubyP50500017717Nagpur (M Corp.)2018Certificate Signed30 Mar 202430 Mar 2024On date
Leverage Green Parks - OpalP50500032663Nagpur (M Corp.)2022Certificate Signed31 Mar 202531 Mar 2025On date
Leverage Green Parks Phase-IIP50500077753Nagpur (M Corp.)2024Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • OnyxOn date
  • RubyOn date
  • Leverage Green Parks - OpalOn date
  • Leverage Green Parks Phase-II+4 mo

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Leverage Green Parks Phase-II (P50500077753).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology