RERA projects in Kinhi(Dhanoli)
3 projects under 3 MahaRERA registrations, registered 2024–2026. 33% have a completion date extended beyond the one promised.
Locality
3RERA projects
3Registrations
3Completion still due0 past their completion date
4 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2024 | 1 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Kinhi(Dhanoli)
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sarla Nagri-IISarla Builders & Developers Aop | PP1190002601605 | 21 Aug 2026 | 27 Jul 2031 | 27 Jul 2031 | Not yet due | 0 |
| Laxmi Nagar-5M/s Shree Realtors | PP1190002501727 | 9 Dec 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Sarla NagriSarla Developers Aop | P50500054987 | 21 Feb 2024 | 20 Nov 2028 | 20 Nov 2028 | Not yet due | 0 |
Other localities in Hingna
Most active promoters
By projects registered here, as named on MahaRERA.
- M/s Shree Realtors1 project
- Sarla Builders & Developers Aop1 project
- Sarla Developers Aop1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology