RERA projects in Kalmeshwar (Mcl)

8 projects under 8 MahaRERA registrations, registered 2017–2026. 38% have a completion date extended beyond the one promised.

8RERA projects
8Registrations
4Completion still due4 past their completion date, 1 marked completed
22 monthsMedian extension beyond promised date38% of registrations extended
0Regulatory casesnone on MahaRERA's lists
11Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20180
20190
20201
20211
20220
20231
20240
20250
20263

Projects in Kalmeshwar (Mcl)

8 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Bhagyalaxmi PrimeSaubhagyasarita Reality LLPPR119000260123620 Jul 202630 Jun 2028—Not yet due0
Ram Nagar 7Ashish Ramraoji BobadePP11900026010918 Jul 202631 Dec 2030—Not yet due0
Manik Nagari Dream CityUnique Associate Infra DevelopersPP119000250251526 Feb 202631 Dec 2028—Not yet due0
SangamKailas Deonathji Gurao And Rajendra Vinayak BaheP5050005233414 Aug 202331 Dec 2027—Not yet due0
Bhagirath MangalamShrigopal Rameshkumar Sales Private LimitedP5050002823018 Feb 202130 Dec 20237 Jan 2025Extended 13 mo0
Shivaji ComplexAdditya InfrastructureP5050002449118 Feb 202030 Dec 2022—Promised date passed0
Vidarbha Premier Nagri Phase 3 KalmeshwarPrakash Narayanrao RaoleP5050001047731 Aug 201731 Dec 201830 Oct 2020Completed0
Kasturi AppartmentsSky Developers And Promoters India Pvt. Ltd.P5050000085623 Jul 201731 Dec 201930 Dec 2021Extended 24 mo0

Other localities in Kalameshwar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Additya Infrastructure1 project
  2. Ashish Ramraoji Bobade1 project
  3. Kailas Deonathji Gurao And Rajendra Vinayak Bahe1 project
  4. Prakash Narayanrao Raole1 project
  5. Saubhagyasarita Reality LLP1 project
  6. Shrigopal Rameshkumar Sales Private Limited1 project
  7. Sky Developers And Promoters India Pvt. Ltd.1 project
  8. Unique Associate Infra Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology