Hingna, Nagpur
Deedo IDDL-NGP-HINGNA6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects351
Registrations368some projects hold several
Completion still due229109 past their date
Median extension4 months46% of registrations extended
Regulatory cases6on 5 projects
6 in 10 registrations run late here
368 MahaRERA registrations in Hingna and the places within it
19 completed92 not yet due132 extended, not yet due95 past even the latest date30 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Hingna
351 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Nagpur MarinaHOABL Impactum Land Private Limited | Due Apr 2029, extended 4 mo | — | — |
| Anandam Elite - Isasani 87Rajesh Amrutlal Vasani | Due Apr 2028, extended 4 mo | — | — |
| Harbans Park Phase 3Harbans Creation (Aop) | Due Apr 2028, extended 4 mo | — | — |
| Laxmi Nagar-5Shree Realtors | Due Apr 2030, extended 4 mo | — | — |
| Flora GreensGomati Associates | Due Apr 2029, extended 4 mo | — | — |
| Silver Star - 6Tirupati Developers | Due Mar 2031, extended 4 mo | — | — |
| Shivaji Kingdom City 5Sudarshan Developers | Due Apr 2032, extended 4 mo | — | — |
| Dada DhamSuresh Vitthalrao Kurode(HUF) | Due Apr 2031, extended 4 mo | — | — |
| Narmada Vihar-10Ritesh Radheshyam Sharma | Due Apr 2030, extended 4 mo | — | — |
| Mahalaxmi Nagar- 45 Sector- 1Rohit Iron And Steel I Pvt Ltd | Due Dec 2030, extended 4 mo | — | — |
| Vijaya SaraswatiThe Squarefeet Company | Due Dec 2028 | — | — |
| Mahalaxmi Nagar - 45 : Sector 2Mahalaxmi Infracon | Due Dec 2030, extended 4 mo | — | — |
| Shreenidhi Estate-VIShri Sai Builders And Developers | Due Dec 2030 | — | — |
| Global City - ISUKHADAS PARDHI, OMPRAKASH PARDHI, RANJANA KADWE, VAIDEHI KADWE and JAY KADWE | Due Apr 2030, extended 4 mo | — | — |
| Pp1190002501187Vidarbha Patbandhare Karmachari Sahakari Pat Sanstha Maryadit | Due Dec 2028 | — | — |
| Silver Star - 5Tirupati Developers | Due May 2030, extended 4 mo | — | — |
| Raghukul ParkSanjay Ramkrushna Jagtap | Due Jan 2031 | — | — |
| Vrindavan ParkTirupati Developers, Tirupati Developers | Due Jan 2031 | — | — |
| Raghukul Park-4Sanjay Ramkrushna Jagtap | Due Jul 2030 | — | — |
| Paradise ParkPradeep Harisingh Gour | Due Jul 2031, extended 4 mo | — | — |
| Britain Empire IIAtul M Yamsanwar | Due Sep 2030, extended 4 mo | — | — |
| Tulsi Nagari-IITarasingh Bhimsingh Rajput | Due Jul 2028, extended 4 mo | — | — |
| Royal VistaRoyal Fort Developers | Due Jun 2029, extended 4 mo | — | — |
| Kanchan Nagari - 15Swami Infra | Due Apr 2028, extended 4 mo | — | — |
| Tulsi Nagari-ITarasingh Bhimsingh Rajput Hanumansingh Bhimsingh Rajput and Bhaiyyalal Singh Bhimsingh Rajput | Due Jul 2028, extended 4 mo | — | — |
Nearby: other talukas in Nagpur
Most active promoters
- Tirupati Developers23 projects
- Mahalaxmi Infracon9 projects
- L G Developers And Builders5 projects
- MHADA (Nagpur board)4 projects
- M & R Infra Pavers Private Limited4 projects
- Shubh Infrastructure4 projects
- Gomati Associates3 projects
- Jagdishprasad Hanumnmal Sharma3 projects
- Ritesh Kailashprasad Saxena3 projects
- Ritesh Radheshyam Sharma3 projects
Hingna, in questions
How many projects in Hingna run late?
6 in 10 MahaRERA registrations (227 of 368): their completion date was extended or has passed, data through 29 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Hingna by Deedo. Medians on fewer than 3 deeds are not shown.
Data through29 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology