Metro Square

Lapsed

Butibori, Nagpur 441108 |Promoter: P.n.b.construction Company

7 Sep 2017Registered with MahaRERA
30 Jun 2021Promised completion
1Building
111Units registered
2MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Lapsed
Buildings
1
Unit types
Shops and rooms111 units in all
Land area for this project
3,000 sq m (32,292 sq ft)
Permissible built-up area
4,500 sq m (48,438 sq ft)
Sanctioned built-up area
2,884 sq m (31,043 sq ft)
Recreational open space
3,000 sq m (32,292 sq ft)
Address
X-1, PIN 441108
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.50353, 73.76154
Metro Square is at latitude 18.50353, longitude 73.76154.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2021

The latest completion date on record passed 5 years and 4 months ago.

Registered
7 Sep 2017
Promised
30 Jun 2021

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P505000128157 Sep 201730 Jun 2021—P.n.b.construction CompanyProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Metro Square8111

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

111 units registered

Shops and rooms · 111 units
TypeCarpet areaUnits
Shops and rooms2,360 sq m · 25,403 sq ft111

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Metro Square

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure75%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
  • Sanitary Fittings within the flats / premises75%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyMIDC100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)DONE100%
  • Storm Water DrainsDONE100%
  • Landscaping & Tree PlantingWORK IN PROGRESS100%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingWORK IN PROGRESS50%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsWORK IN PROGRESS90%
  • Electrical meter room, sub-station, receiving stationWORK IN PROGRESS50%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

14 documents held by Deedo, 17 filings listed on MahaRERA's project page

Title

Encumbrance

Form 1

Form 2

Form b

Commencement certificate

Form 5

Registration certificate

Completions

Others

Layout plan

Allotment letter

Document library

  • Copy of the legal title reportLegal Reports.pdf · uploaded 8 Aug 2017View
  • Details of encumbrancesEncumbrance Bank.pdf · uploaded 8 Aug 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Archietect certificate_Form 1.pdf · uploaded 8 Aug 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate form 2.pdf · uploaded 8 Aug 2017View
  • Proforma of Allotment letterProforma of Allotment Letter.pdf · uploaded 27 Aug 2017View
  • Declaration in FORM Bform b PNB.pdf · uploaded 31 Aug 2017View
  • Building Plan Approval (IOD)combinepdf.pdf · uploaded 31 Aug 2017View
  • Copy of Layout Approval (in case of layout)combinepdf.pdf · uploaded 31 Aug 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 28 Apr 2018View
  • Certificates of CA (Form 5)form 5 PNB.pdf · uploaded 29 Sep 2018View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentForm 4.pdf · uploaded 8 Jan 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate.pdf · uploaded 8 Jan 2022View

Promoter documents

  • Legal Title reportLegal Reports.pdf · uploaded 8 Aug 2017View
  • Declaration Form Bform b PNB.pdf · uploaded 31 Aug 2017View

Technical documents

  • Building Plan Approvalcombinepdf.pdfView
  • Layout Approvalcombinepdf.pdfView

Proforma allotment letter

  • Proforma allotment letterProforma of Allotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Butibori, Nagpur (Rural) taluka

Survey, CTS, gat or plot numbers

X1

As published on MahaRERA's project page

X-1,

Boundaries

North
Plot Number Two
South
Sixty Meter Wide Road
East
Twenty Meter Road
West
Hotel Mayur Plot No X Ten

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGautam M Sontakke—
Chartered accountantGirish Chandak—
EngineerAman Kumar—
OtherNeklal Gautam—

Source: MahaRERA project page. Contact details are not shown.