4 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects515
Registrations517some projects hold several
Completion still due189283 past their date
Median extension4 months43% of registrations extended
Regulatory cases10on 10 projects
Satara market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

8 in 10 registrations run late here

517 MahaRERA registrations in Satara and the places within it

43 not yet due146 extended, not yet due283 past even the latest date45 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Satara

515 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Dwarka NagariShivshahi Builders And DevelopersPR130000260245719 Oct 202631 Dec 2032—Not yet due0
Nirav HeightsNavnirrmitii Builders And Developers LLPPM130000260244219 Oct 202631 Dec 2030—Not yet due0
Gajanan PrideGajanan Shinde Builders & DevelopersPR130000260236816 Oct 202631 Dec 2031—Not yet due0
Moraya VishwaKumar Balasaheb ChavanPR13000026021777 Oct 202631 Dec 202931 Dec 2029Not yet due0
Navnirrmitii SquareNavnirrmitii Builders And Developers LLPPM13000026021435 Oct 202631 Dec 203031 Dec 2030Not yet due0
Emerald HeightsVishal Dilip PawarPR13000026020681 Oct 202631 Dec 203231 Dec 2032Not yet due0
Sargam HeightsK K DevelopersPR130101260201123 Sep 202631 Mar 203231 Mar 2032Not yet due0
Mangalmurti ComplexSankalp DevelopersPM130000260199622 Sep 202631 Dec 203231 Dec 2032Not yet due0
Shreeji EliteJagtap Devi AssociatesPR13000026017924 Sep 202631 Dec 203131 Dec 2031Not yet due0
Radhakrushna EmpireShree Balaji Builders And DeveloperPR130000260159921 Aug 202630 Jun 203130 Jun 2031Not yet due0
Samarveer SkylineShri Mangalmurti BuildersPR130000260156317 Aug 202631 Dec 203331 Dec 2033Not yet due0
Reliable PrideReliable AssociatesPR13000026014023 Aug 202631 Dec 203131 Dec 2031Not yet due0
Shree Keshav ResidencyShree Dwarka DevelopersPR130000260131727 Jul 202631 Dec 203030 Apr 2031Extended 4 mo0
VivantaD Cube Buildcon LLPPM130000260078715 Jun 202631 Dec 202930 Apr 2030Extended 4 mo0
Viraj ParkVs InfraPR130000260054025 May 202631 Dec 203130 Apr 2032Extended 4 mo0
Unique LandmarkAkshad Infrastructure And DevelopersPR130000260044717 May 202631 Dec 203030 Apr 2031Extended 4 mo0
River CountyS B GroupPR130000260039411 May 202614 Feb 203214 Jun 2032Extended 4 mo0
Saavi The Heart Of VikasnagarSaavi The Heart Of VikasnagarPR130000260010315 Apr 202631 Dec 203030 Apr 2031Extended 4 mo0
Indu EliteLandmark Builders And DevelopersPR130000260006810 Apr 202631 Dec 203030 Apr 2031Extended 4 mo0
Bajirao EmpireShree Sheshachal DevelopersPR130000250305427 Mar 202631 Dec 203130 Apr 2032Extended 4 mo0
Narayan AshwiniAbasaheb Jare ConstructionPR130000250289718 Mar 202631 Dec 203030 Apr 2031Extended 4 mo0
Anvi PearlAmol Barge And AssociatesPR130000250286617 Mar 202631 Dec 203130 Apr 2032Extended 4 mo0
ShivsaiDream Vision PropertiesPR130000250284116 Mar 202631 Dec 202930 Apr 2030Extended 4 mo0
Moon Light TowerRaj BuildersPR130000250274912 Mar 202631 Dec 203030 Apr 2031Extended 4 mo0
Sukhodayam VillasM/s Ultra Urban Greene Realty LLPPP130000250270110 Mar 202631 Dec 202730 Apr 2028Extended 4 mo0

Most active promoters

  1. Aditya Developers through Proprietor Kumar Balasaheb Chavan5 projects
  2. ASHWINI BUILDER'S & DEVELOPERS Pvt. Ltd.5 projects
  3. Shree Chaitanya Builders5 projects
  4. Model Developers And Builders4 projects
  5. M Sons Builder And Developers4 projects
  6. Shinde Jadhav Builders And Developers4 projects
  7. Varad Builders and Promoters4 projects
  8. Avani Infrastructure3 projects
  9. Kachhi Properties3 projects
  10. Niketan Construction3 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology