Nahur, Mumbai Suburban

Deedo IDDL-MSB-NAHUR

8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects24
Registrations25some projects hold several
Completion still due232 past their date
Median extension4 months76% of registrations extended
Regulatory cases1on 1 project

8 in 10 registrations run late here

25 MahaRERA registrations in Nahur

4 not yet due19 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Nahur

24 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Axiom GloriaAxiom Refab Construction (India) Pvt LtdDue Jul 2030, extended 4 mo——
Sai VenusRmt CombineDue Apr 2029, extended 4 mo——
Nahur Villa Cottage CHSLOrange Nirman Realtors LLPDue Sep 2028, extended 4 mo——
Pradhan Chsl (Om Sumukha)Sumukha Ventures LLPDue Sep 2027, extended 4 mo——
Jay Ashapura ChslSumukha DevelopersDue Apr 2028, extended 4 mo——
All 24 projects →
Nahur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Axiom Refab Construction (India) Private Limited3 projects
  2. Avs Housing And Construction Llp2 projects
  3. Alliance City Developers Realtors Pvt Ltd1 project
  4. Arkade Developers Private Limited1 project
  5. Atul Projects India Private Limited1 project
  6. Castle Floors PMS Pvt Ltd1 project
  7. Contendre Infratech Pvt. Ltd1 project
  8. Dream Constructions1 project
  9. Duratech1 project
  10. Harmony Homes Creation1 project

Nahur, in questions

How many projects in Nahur run late?

8 in 10 MahaRERA registrations (21 of 25): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nahur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology