Mohili, Mumbai Suburban

Deedo IDDL-MSB-MOHILI

8 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects6
Registrations6
Completion still due51 past their date
Median extension4 months83% of registrations extended
Regulatory cases0none on MahaRERA's lists
Mohili market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

10 in 10 registrations run late here

6 MahaRERA registrations in Mohili

5 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Mohili

6 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Elite BlissSh Elite DevelopersDue Oct 2029, extended 4 mo——
Crescent Wtc T2 Phase IICrown Realty Developers Private LimitedDue Dec 2028, extended 4 mo——
Crescent Western Trade Center - T2Crown Developers LLPDue Apr 2028, extended 4 mo—0%
Sona HeightsSumukha Realtors & DevelopersDue Nov 2027, extended 4 mo—0%
Somani 72 EastNircon Developers Pvt LtdDue Apr 2027, extended 4 mo——
Pr HeightsPankhi Reliable Developers LLP1 yr 7 mo late—87%

Most active promoters

  1. Crown Developers LLP1 project
  2. Crown Realty Developers Private Limited1 project
  3. Nircon Developers Pvt Ltd1 project
  4. Pankhi Reliable Developers LLP1 project
  5. Sh Elite Developers1 project
  6. Sumukha Realtors & Developers1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology