Mohili, Mumbai Suburban
Deedo IDDL-MSB-MOHILI8 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects6
Registrations6
Completion still due51 past their date
Median extension4 months83% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
6 MahaRERA registrations in Mohili
5 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Mohili
6 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Elite BlissSh Elite Developers | Due Oct 2029, extended 4 mo | — | — |
| Crescent Wtc T2 Phase IICrown Realty Developers Private Limited | Due Dec 2028, extended 4 mo | — | — |
| Crescent Western Trade Center - T2Crown Developers LLP | Due Apr 2028, extended 4 mo | — | 0% |
| Sona HeightsSumukha Realtors & Developers | Due Nov 2027, extended 4 mo | — | 0% |
| Somani 72 EastNircon Developers Pvt Ltd | Due Apr 2027, extended 4 mo | — | — |
| Pr HeightsPankhi Reliable Developers LLP | 1 yr 7 mo late | — | 87% |
Nearby: other localities in Kurla
Most active promoters
- Crown Developers LLP1 project
- Crown Realty Developers Private Limited1 project
- Nircon Developers Pvt Ltd1 project
- Pankhi Reliable Developers LLP1 project
- Sh Elite Developers1 project
- Sumukha Realtors & Developers1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology