The 1925
Deedo IDDP-MUM-5PD8MahaRERA shows it completed; no MahaRERA orders on record; 95% of its units are booked.
Ward Abcd, Maharashtra 400004 · by Suparshva Incorporation
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 15 May 2020, completion promised 30 Sep 2024.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51900025387
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51900025387 | 15 May 2020 | 30 Sep 2024 | 30 Sep 2024 | Suparshva Incorporation | Project page |
Documents57
1 document held by Deedo, 56 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD SUPARSHVA-converted.pdf · uploaded 5 May 2020Source
Legal
Migrated
- 1 PAN CardPAN CARD SUPARSHVA-converted.pdf · uploaded 5 May 2020Source
- 1 Copy of the legal title reportTItle Report 1.pdf · uploaded 5 May 2020Source
- 1 Copy of Layout Approval (in case of layout)Drawing.pdf · uploaded 5 May 2020Source
- 1 Commencement Certificates / NA Order for plotted development2224780_FirstCC_signed.pdf · uploaded 5 May 2020Source
Show all 57 documentsShow fewer documents
Migrated
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Rera Certificate.pdf · uploaded 5 May 2020Source
- 1 Details of encumbrancesEncumbrances Letter.pdf · uploaded 7 May 2020Source
- 1 Declaration in FORM BDeclaration Form B.pdf · uploaded 7 May 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentIOD NEW .pdf · uploaded 8 May 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentIOD NEW 2.pdf · uploaded 8 May 2020Source
- 3 Building Plan Approval / NA Order for plotted developmentPlans 3.pdf · uploaded 8 May 2020Source
- 1 Proforma of Allotment letterdraft allotement letter rera.pdf · uploaded 8 May 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 1925.pdf · uploaded 14 Apr 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 The 1925 31st March 2021_compressed.pdf · uploaded 14 Apr 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 1925 2020-21.pdf · uploaded 16 Apr 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Certificate 282.pdf · uploaded 30 Sep 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentLatest CC.pdf · uploaded 12 Oct 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 as on March 2022.pdf · uploaded 12 Oct 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)New format- Form 3 The 1925 31st March 2022.pdf · uploaded 12 Oct 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_The 1925.pdf · uploaded 15 Nov 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- The 1925 as on June 2022.pdf · uploaded 15 Nov 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- The 1925 as on September 2022.pdf · uploaded 15 Nov 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- The 1925 as on June 2022.pdf · uploaded 15 Nov 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 The 1925 as on June 2022.pdf · uploaded 15 Nov 2022Source
- 1 CERSAI detailsThe 1925.pdf · uploaded 26 Nov 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- The 1925 as on December 2022.pdf · uploaded 23 Jan 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 The 1925 31st December 2022.pdf · uploaded 23 Jan 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Apr 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 The 1925 as on 31-03-2023.pdf · uploaded 21 Apr 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2374137_OC_signed.pdf · uploaded 24 Jun 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentLatest Layout-1.pdf · uploaded 21 Jul 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentLatest Layout-2 TO 4.pdf · uploaded 21 Jul 2023Source
- 3 Commencement Certificates / NA Order for plotted developmentLatest CC.pdf · uploaded 21 Jul 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- The 1925 as on 13th Jun 23.pdf · uploaded 21 Jul 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- The 1925 as on 13-06-2023.pdf · uploaded 21 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5_ The 1925 as on 31st March 2023.pdf · uploaded 28 Sep 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 22 Jan 2025Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoc (2).pdf · uploaded 22 Jan 2025Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Architect Completion Certificate RERA (4).pdf · uploaded 27 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 15 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)8 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf · uploaded 15 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 15 Feb 2025Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development3 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for plotted development (19).pdf · uploaded 27 Mar 2025Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development4 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for plotted development (7).pdf · uploaded 14 Jun 2025Source
Technical
- DocumentDrawing.pdf · uploaded 5 May 2020Source
- DocumentIOD NEW .pdf · uploaded 8 May 2020Source
- DocumentIOD NEW 2.pdf · uploaded 8 May 2020Source
- DocumentPlans 3.pdf · uploaded 8 May 2020Source
- DocumentLatest Layout-1.pdf · uploaded 21 Jul 2023Source
- DocumentLatest Layout-2 TO 4.pdf · uploaded 21 Jul 2023Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 1105
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK20 units in all
- Address
- 1105, Junction of Khetwadi Main Road and 11th Khetwadi Road, Charni Raod EastPIN 400004
- Land area for this project
- 522 sq m (5,624 sq ft)
- Permissible built-up area
- 4,467 sq m (48,087 sq ft)
- Sanctioned built-up area
- 4,421 sq m (47,592 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
1105
Boundaries
- North
- The property formerly of Shapurji B Broacha
- South
- The Khetwadi Main Road
- East
- The Khetwadi 11th Lane
- West
- The property formerly of Shapurji B Broacha
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking20 units
19 of 20 units booked (95%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 52.68 sq m · 567 sq ft | 3 | 3 |
| 1BHK | 52.95 sq m · 570 sq ft | 1 | 1 |
| 2BHK | 64.85 sq m · 698 sq ft | 8 | 7 |
| 2BHK | 68.47 sq m · 737 sq ft | 3 | 3 |
| 2BHK | 71.81 sq m · 773 sq ft | 3 | 3 |
| 2BHK | 76.64 sq m · 825 sq ft | 1 | 1 |
| 3BHK | 87.14 sq m · 938 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Rutuja Narsingh & Associates | — |
| Chartered accountant | V Can And Company | — |
| Engineer | SK Consultants & Engineers | — |
| Other | RERA Easy | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Ward Abcd
- Kinjal LegacyRERA PR1170002601342
- Jayant SkyRERA PM1170002601188
- Trithiya SerenityRERA PR1170002600740
- Golden NavkarRERA PR1170002600539
- Nexus IXRERA PC1170002503022
- Shukriya Elite TowerRERA PM1170002502856
- Imperial T3 Wing CRERA PR1171012502413
- Aurum GirnarRERA P51900080926
All 156 projects in Ward Abcd · Compare The 1925 with another project