Extended 4 mo7 floors · 18 flatsRERA P53000080005
Building B, Dhanashree Svasti
Deedo IDDP-KOL-RJWD-B2 flats have a sale on record, 4 are booked without a sale deed yet and 4 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
Median saleNot on recordneeds 3 or more sales
Booked33%6 of 18 · Oct 2026
Completion30 Apr 202931 Dec 2028 · revised
Every flat, floor by floor
Tap a flat to see its record.
- Sale registered
- Booked, no deed yet
- Unsold
- Reserved, rehab or other
010203040506
Fl 7
Fl 6
Fl 5
Fl 4
Fl 3
Fl 2
Fl 1
2 BHK2 BHK
Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
SelectedUnsold
Flat B101
1 RK B101 SALE · 415 sq ft · Wing B · floor 1
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Building B
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK B102 LANDOWNER | 45.6 m² (490 sq.ft) | 1 | 0 |
| 1RK B101 SALE | 38.6 m² (415 sq.ft) | 1 | 0 |
| 2BHK A403 SALE | 77 m² (829 sq.ft) | 1 | 0 |
| 2BHK B103 LANDOWNER | 74.8 m² (805 sq.ft) | 1 | 0 |
| 2BHK B105 SALE | 77 m² (829 sq.ft) | 1 | 0 |
| 2BHK B106 LANDOWNER | 69.2 m² (745 sq.ft) | 1 | 0 |
| 2BHK B203 LANDOWNER | 77 m² (829 sq.ft) | 1 | 0 |
| 2BHK B204 LANDOWNER | 72 m² (775 sq.ft) | 1 | 0 |
| 2BHK B303 SALE | 77 m² (829 sq.ft) | 1 | 0 |
| 2BHK B304 LANDOWNER | 75.4 m² (812 sq.ft) | 1 | 0 |
| 2BHK B404 SALE | 75.4 m² (812 sq.ft) | 1 | 0 |
| 3BHK A402 LANDOWNER | 94.9 m² (1,021 sq.ft) | 1 | 0 |
| 3BHK B201 LANDOWNER | 90.5 m² (974 sq.ft) | 1 | 0 |
| 3BHK B202 SALE | 94.9 m² (1,021 sq.ft) | 1 | 0 |
| 3BHK B301 SALE | 94.3 m² (1,015 sq.ft) | 1 | 0 |
| 3BHK B302 LANDOWNER | 94.9 m² (1,021 sq.ft) | 1 | 0 |
| 3BHK B401 SALE | 94.3 m² (1,015 sq.ft) | 1 | 0 |
| STUDIO B104 SALE | 27.9 m² (301 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P53000080005 · registered 17 Apr 2025
- Promised completion
- 31 Dec 2028
- Revised completion
- 30 Apr 2029
- Sanctioned habitable floors
- 7
- Sanctioned floors (incl. basement, stilt, podium)
- 8
- Units declared
- 18
- Homes
- 18
- Shops and offices
- 0
- Sanctioned FSI area (sq m)
- 4
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-KOL-RJWD-B
Questions about Building B
How many flats in Building B are sold?
2 flats have a sale on record, 4 are booked without a sale deed yet and 4 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
When is Building B due for completion?
The MahaRERA registration promises 31 Dec 2028, revised to 30 Apr 2029.
How many floors does Building B have?
7 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology