Extended 22 mo9 floorsRERA P53000006212
Main building, Hiranyakeshi Complex
Deedo IDDP-KOL-1DZY-HCMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked51%45 of 88 · MahaRERA
Completion30 Oct 202031 Dec 2018 · revised
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 33.1 m² (357 sq.ft) | 6 | 4 |
| 1BHK | 34.5 m² (371 sq.ft) | 2 | 1 |
| 1BHK | 35.2 m² (379 sq.ft) | 6 | 6 |
| 1BHK | 35.4 m² (381 sq.ft) | 3 | 2 |
| 1BHK | 35.4 m² (381 sq.ft) | 3 | 2 |
| 1BHK | 35.6 m² (383 sq.ft) | 3 | 3 |
| 1BHK | 35.6 m² (383 sq.ft) | 3 | 2 |
| 1BHK | 36.4 m² (392 sq.ft) | 3 | 3 |
| 1BHK | 37.7 m² (405 sq.ft) | 2 | 2 |
| 1BHK | 37.9 m² (408 sq.ft) | 3 | 2 |
| 1BHK | 37.9 m² (408 sq.ft) | 1 | 0 |
| 1BHK | 38 m² (409 sq.ft) | 2 | 2 |
| 1BHK | 38.9 m² (419 sq.ft) | 1 | 1 |
| 1BHK | 40.4 m² (434 sq.ft) | 2 | 2 |
| 1BHK | 40.5 m² (436 sq.ft) | 1 | 1 |
| 1BHK | 40.5 m² (436 sq.ft) | 1 | 1 |
| 1RK | 23.5 m² (252 sq.ft) | 2 | 1 |
| 1RK | 23.9 m² (258 sq.ft) | 1 | 0 |
| 1RK | 25.9 m² (279 sq.ft) | 2 | 1 |
| 1RK | 26.4 m² (284 sq.ft) | 1 | 1 |
| 2BHK | 55.6 m² (599 sq.ft) | 2 | 1 |
| 2BHK | 56.4 m² (608 sq.ft) | 2 | 1 |
| 2BHK | 64.3 m² (692 sq.ft) | 2 | 2 |
| SHOP | 14.2 m² (152 sq.ft) | 4 | 0 |
| SHOP | 14.9 m² (160 sq.ft) | 4 | 0 |
| SHOP | 15.7 m² (169 sq.ft) | 4 | 1 |
| SHOP | 17 m² (182 sq.ft) | 12 | 1 |
| SHOP | 18.4 m² (198 sq.ft) | 2 | 1 |
| SHOP | 19.4 m² (209 sq.ft) | 2 | 0 |
| SHOP | 20.1 m² (216 sq.ft) | 2 | 0 |
| SHOP | 23.1 m² (248 sq.ft) | 4 | 1 |
As registered with MahaRERA
- RERA registration
- P53000006212 · registered 14 Aug 2017
- Promised completion
- 31 Dec 2018
- Revised completion
- 30 Oct 2020
- Sanctioned habitable floors
- 9
- Building
- HIRANYAKESHI COMPLEX
- Sanctioned floors (incl. basement, stilt, podium)
- 9
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-KOL-1DZY-HC
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 31 Dec 2018, revised to 30 Oct 2020.
How many floors does Main building have?
9 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology