Uma Realty
Deedo IDDD-SBWBOf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
3 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| ElementsP51700015118 | Thane (M Corp.) | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 mo |
| ElementsP51700016716 | Thane (M Corp.) | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| ElementsP51700022580 | Thane (M Corp.) | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| ElementsP51700079384 | Daighar | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
| ElementsP51700079654 | Daighar | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 mo |
Uma Realty, in questions
Does Uma Realty finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Uma Realty registered with MahaRERA?
2 projects under 5 MahaRERA registrations; 3 completed on MahaRERA.
Does Uma Realty have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.