Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P51700079654

Elements · Thane (M Corp.), Thane · Uma Realty

Promised for 31 Mar 2029, extended to 31 Jul 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2029 to 31 Jul 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate20 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700079654

Is Elements delayed?

Its completion moved from 31 Mar 2029 to 31 Jul 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700079654. The completion date moved from 31 Mar 2029 to 31 Jul 2029.

Who is the promoter?

MahaRERA records Uma Realty as the promoter of P51700079654.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700079654.

Answers are generated from the record.

Data through28 Oct 2026, 03:11SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology