Sunteck Realty Holdings Pvt Ltd
Deedo IDDD-FCH0Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 5 mo late.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sunteck FORESTWorldP51700030578 | Khativali | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Sunteck FORESTWorldP51700030580 | Khativali | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Sunteck FORESTWorldP51700030607 | Khativali | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +5 mo* |
| Sunteck FORESTWorld 4P51700030819 | Khativali | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Sunteck Realty Holdings Pvt Ltd, in questions
Does Sunteck Realty Holdings Pvt Ltd finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sunteck Realty Holdings Pvt Ltd registered with MahaRERA?
2 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Sunteck Realty Holdings Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.