RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51700030580

Sunteck FORESTWorld · Khativali, Thane · Sunteck Realty Holdings Pvt Ltd

Promised for 31 Dec 2025 — that date has passed and MahaRERA does not mark the project complete.

11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2025, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate1 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700030580

Is Sunteck FORESTWorld delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700030580.

Who is the promoter?

MahaRERA records Sunteck Realty Holdings Pvt Ltd as the promoter of P51700030580.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700030580.

Answers are generated from the record.

Data through16 Nov 2026, 02:04SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology