Space India Builders & Developer
Deedo IDDD-5KP4Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 10 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Space Gold CrestP52000017546 | Mamdapur | Certificate Signed | 30 Dec 2020 | 30 Apr 2022 | +16 mo |
| Space GreensP52000032326 | Dundre | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| AmulyamP52000034022 | Pale Bk. | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
Space India Builders & Developer, in questions
Does Space India Builders & Developer finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 10 mo late. Across Maharashtra, 73% kept their date.
How many projects has Space India Builders & Developer registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Space India Builders & Developer have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.