Company or firm · first RERA registration 2018

Shubhankar Developers

Deedo IDDD-X599

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Royal ResidencyP52600014907Barshi (M Cl)Certificate Signed30 Dec 202230 Dec 2022On date
Royal Residency Building No 2P52600053463BarshiCertificate Signed31 Mar 202631 Mar 2026On date
Royal Residency Building No 4PR1320002600339Barshi (M Cl)Certificate Signed31 Dec 202730 Apr 2028+4 mo

Shubhankar Developers, in questions

Does Shubhankar Developers finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Shubhankar Developers registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Shubhankar Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology