Royal Residency Building No 4 · Barshi (M Cl), Solapur · Shubhankar Developers
Promised for 31 Dec 2027, extended to 30 Apr 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about PR1320002600339
Is Royal Residency Building No 4 delayed?
Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for PR1320002600339. The completion date moved from 31 Dec 2027 to 30 Apr 2028.
Who is the promoter?
MahaRERA records Shubhankar Developers as the promoter of PR1320002600339.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names PR1320002600339.