Shree Ostwal Builders Ltd
Deedo IDDD-8NQ3Of 8 registrations whose promised date has arrived, 5 kept it (63%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
14 of 20 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 20 registrations
20 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ostwal DarshanP51700004905 | Mirabhayandar (M Corp.) | Certificate Signed | 30 Dec 2023 | 29 Dec 2024 | +12 mo |
| Ostwal ValleyP99000006087 | Katkar (Ct) | Certificate Signed | 31 Jul 2019 | 31 Jul 2019 | On date |
| Ostwal Wonder CityP99000006909 | Betegaon | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Ostwal PointP51700008381 | Mirabhayandar (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Ostwal Height - 5P51700008433 | Mirabhayandar (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Ostwal Dream LandP99000008545 | Boisar | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Ostwal WoodsP99000019832 | Palghar | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Ostwal Dream LandP99000021182 | Boisar | Certificate Signed | 31 Jul 2026 | 30 Nov 2026 | +4 mo |
| Ostwal HorizonP51700024492 | Mirabhayandar (M Corp.) | Certificate Signed | 30 Dec 2028 | 30 Apr 2029 | +4 mo |
| Ostwal PalaceP99000034236 | Palghar | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Ostwal Paradise Building No.9 Wing A - B - CP51700048041 | Thane | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Ostwal ImperialP99000049283 | Palghar | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Ostwal VillasP99000051610 | Palghar | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Ostwal WoodsP99000056093 | Betegaon | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Ostwal Gala KunjP51800077808 | Mulund | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
| Ostwal ParamountP99000078147 | Boisar | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
| Ostwal AkaashaP51700079129 | Bhayandar | Certificate Signed | 31 Dec 2029 | 31 Dec 2029 | On date |
| Ostwal WoodsP99000080244 | Betegaon | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
| Ostwal MansionPM1330002501323 | Bhayandar | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
| Ostwal FerminoPR1180002502949 | Eksar | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
Show all 20 registrationsShow fewer
Shree Ostwal Builders Ltd, in questions
Does Shree Ostwal Builders Ltd finish projects on time?
Of 8 MahaRERA registrations whose promised completion date has arrived, 5 kept it (63%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Ostwal Builders Ltd registered with MahaRERA?
18 projects under 20 MahaRERA registrations; 7 completed on MahaRERA.
Does Shree Ostwal Builders Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.