Shree Enterprises

Company or firm · 6 projects · 7 MahaRERA registrations

Projects67 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sparsh ZinneaP52100011767Kasar Amboli2017Not reported31 Dec 202731 Dec 2027On date
SparshP52000016230Shedung2018Not reported30 Mar 202231 Dec 2025+45 months
SparshP52000027334Shedung2020Not reported30 Jun 2025—On date
ShivKripa CHS Ltd.P51800032765Andheri2022Not reported31 Dec 2023—On date
Sparsh AsterP52100035183Kasar Amboli2022Not reported31 Dec 2026—On date
Jayram Residency Phase-IIP52000078204Shedung2024Not reported31 Dec 2028—On date
Shree Empire PlazaPM1270002501457Dapoli2025Not reported31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sparsh ZinneaOn date
  • Sparsh+45 mo
  • SparshOn date
  • ShivKripa CHS Ltd.On date
  • Sparsh AsterOn date
  • Jayram Residency Phase-IIOn date
  • Shree Empire PlazaOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 45 months, for Sparsh (P52000016230).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology